# Component Name Unit TOTAL First Phase New Road (Stage I & II) Briddle Road Reconstruction Motor Bridge Briddle Bridge Building New Road (Stage I) New Road (Stage II) Other First Phase Bridge
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
1 PART 2 KM 255.94 68.76 22.57 76.26 - - - - 177.670 21.090 7.900 45.490 5.000 5.000 2.500 2.500 32.785 9.690 5.000 12.000 - - - - - - - - - - - - 3.000 0.000 0.000 0.000 37.350 32.850 7.170 16.270 0.130 0.130 0.000 0.000 - - - -
2 BM KM 13.28 13.28 12.37 12.37 - - - - - - - - - - - - 12.570 12.570 12.370 12.370 - - - - - - - - - - - - - - - - 0.710 0.710 0.000 0.000 - - - - - - - -
3 Bridge No 18.00 12.00 5.00 5.35 - - - - 4.000 3.000 2.000 2.000 - - - - 0.000 0.000 0.000 0.000 12.000 7.000 2.000 2.350 1.000 1.000 0.000 0.000 - - - - 1.000 1.000 1.000 1.000 - - - - - - - - - - - -
4 Stage KM 85.00 6.00 1.30 2.30 81.000 5.000 0.300 1.300 - - - - - - - - 1.000 0.000 0.000 0.000 - - - - - - - - 1.000 1.000 1.000 1.000 - - - - - - - - - - - - 2.000 0.000 0.000 0.000
5 Building Units no 3.00 3.00 1.50 2.50 - - - - - - - - - - - - - - - - - - - - - - - - 3.000 3.000 1.500 2.500 - - - - - - - - - - - - - - - -
6 New Construction Hill side Cutting Km 432.35 187.07 88.05 225.92 11.500 2.000 2.000 3.600 173.585 21.750 8.550 45.885 - - - - 2.000 2.000 0.000 0.000 - - - - - - - - - - - - 236.785 154.340 71.525 167.455 8.475 6.975 5.975 8.975 - - - - - - - -
7 Widening Improvement Hill side Cutting Km 43.99 43.99 28.78 39.78 - - - - - - - - - - - - 43.990 43.990 28.775 39.775 - - - - - - - - - - - - 0.000 0.000 0.000 0.000 - - - - - - - - - - - -
8 Corner Cutting Km 0.90 0.90 0.90 0.90 - - - - - - - - - - - - 0.900 0.900 0.900 0.900 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
9 Embankment Km 31.98 22.28 22.59 27.24 - - - - 6.150 0.000 0.000 0.000 - - - - 3.000 3.000 3.000 4.200 - - - - - - - - - - - - - - - - 22.830 19.280 19.585 23.035 - - - - - - - -
10 Dumping Zone No 28.00 28.00 0.00 0.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - 28.000 28.000 0.000 0.000 - - - - - - - - - - - -
11 Retaining Wall Rmt 2,292.40 1,489.40 259.00 416.00 - - - - 60.000 60.000 0.000 0.000 - - - - 1,051.000 629.000 164.000 164.000 - - - - - - - - - - - - - - - - 1,181.400 800.400 95.000 252.000 - - - - - - - -
12 Brest Wall Rmt 900.00 900.00 850.00 1,600.00 - - - - 10.000 10.000 0.000 0.000 - - - - 890.000 890.000 850.000 1,600.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
13 Sub Base G1 Km 370.62 294.62 188.17 214.32 0.000 0.000 0.000 0.000 18.320 6.700 7.250 7.250 - - - - 296.410 253.735 150.325 172.775 - - - - - - - - - - - - - - - - 55.889 34.189 30.595 34.295 - - - - - - - -
14 Sub Base GSB Km 77.35 54.38 30.83 35.73 - - - - 6.150 0.000 0.000 0.000 - - - - 45.557 37.051 15.328 19.228 - - - - - - - - - - - - - - - - 25.639 17.329 15.505 16.505 - - - - - - - -
15 Base Course G2 Km 477.56 358.57 199.79 234.72 0.000 0.000 0.000 0.000 24.470 6.300 7.250 7.250 - - - - 379.587 304.526 156.128 183.813 - - - - - - - - - - - - - - - - 73.499 47.739 36.410 43.660 - - - - - - - -
16 Base Course G3 Km 605.54 453.20 214.75 269.34 0.000 0.000 0.000 0.000 24.470 5.900 5.180 5.180 - - - - 499.994 391.100 172.874 218.714 - - - - - - - - - - - - - - - - 81.079 56.199 36.695 45.445 - - - - - - - -
17 DBM Km 32.83 19.99 15.04 24.74 - - - - - - - - - - - - 32.828 19.988 15.038 24.738 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
18 BM Km 38.42 35.55 4.13 6.43 - - - - - - - - - - - - 38.420 35.550 4.130 6.430 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
19 SDBC Km 106.93 91.36 18.57 24.90 - - - - - - - - - - - - 105.930 90.360 18.570 23.870 - - - - - - - - - - - - - - - - 1.000 1.000 0.000 1.030 - - - - - - - -
20 BC Km 64.02 48.43 32.54 43.14 - - - - - - - - - - - - 64.018 48.428 32.538 43.138 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
21 PC Km 569.08 386.43 139.06 173.40 - - - - 20.120 6.400 0.000 0.000 - - - - 490.241 336.396 125.500 156.540 - - - - - - - - - - - - - - - - 58.718 43.638 13.560 16.860 - - - - - - - -
22 DLC PCC Km 13.97 12.85 9.12 9.12 - - - - - - - - - - - - 13.970 12.850 9.120 9.120 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
23 PQC Km 11.17 4.71 0.81 0.81 - - - - - - - - - - - - 11.170 4.710 0.810 0.810 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
24 Interlocking Tile Rmt 176,363.31 108,203.30 78,994.30 103,651.74 - - - - 606.150 600.000 600.000 600.000 - - - - 124,442.300 69,101.300 49,973.300 64,980.735 - - - - - - - - - - - - - - - - 51,314.860 38,502.000 28,421.000 38,071.000 - - - - - - - -
25 Scupper No 159.00 159.00 62.00 72.00 - - - - 3.000 3.000 0.000 0.000 - - - - 97.000 97.000 22.000 22.000 - - - - - - - - - - - - - - - - 59.000 59.000 40.000 50.000 - - - - - - - -
26 Culverts No 67.00 41.00 7.00 11.00 - - - - - - - - - - - - 20.000 11.000 7.000 11.000 - - - - - - - - - - - - - - - - 47.000 30.000 0.000 0.000 - - - - - - - -
27 Cause Way No 9.00 7.00 0.00 0.00 - - - - - - - - - - - - 1.000 1.000 0.000 0.000 - - - - - - - - - - - - - - - - 8.000 6.000 0.000 0.000 - - - - - - - -
28 Unlined Drain Rmt 15,448.00 15,448.00 3,550.00 6,550.00 - - - - - - - - - - - - 9,098.000 9,098.000 2,000.000 5,000.000 - - - - - - - - - - - - - - - - 6,350.000 6,350.000 1,550.000 1,550.000 - - - - - - - -
29 Lined Drain Rmt 10,675.00 10,625.00 7,390.00 7,640.00 - - - - - - - - - - - - 3,100.000 3,050.000 800.000 800.000 - - - - - - - - - - - - - - - - 7,575.000 7,575.000 6,590.000 6,840.000 - - - - - - - -
30 Crash Barrier Rmt 2,697.00 2,654.00 884.00 884.00 - - - - - - - - - - - - 2,697.000 2,654.000 884.000 884.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
31 Parapet No 1,105.00 1,045.00 231.00 234.00 - - - - 26.000 26.000 0.000 0.000 - - - - 420.000 407.000 190.000 193.000 - - - - - - - - - - - - - - - - 659.000 612.000 41.000 41.000 - - - - - - - -
32 Delineators Rmt 35.00 0.00 0.00 0.00 - - - - - - - - - - - - 35.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
33 Sign Board No 108.00 72.00 0.00 0.00 - - - - - - - - - - - - 86.000 50.000 0.000 0.000 - - - - - - - - - - - - - - - - 22.000 22.000 0.000 0.000 - - - - - - - -
34 Abutments LHS No 2.00 1.00 0.00 0.00 - - - - - - - - - - - - - - - - 2.000 1.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
35 Abutments RHS No 2.00 1.00 1.00 1.00 - - - - - - - - - - - - - - - - 2.000 1.000 1.000 1.000 - - - - - - - - - - - - - - - - - - - - - - - -
36 Bearings No 2.00 2.00 2.00 2.00 - - - - - - - - - - - - - - - - 2.000 2.000 2.000 2.000 - - - - - - - - - - - - - - - - - - - - - - - -
37 Steel truss Fabrication Rmt 24.00 0.00 0.00 0.00 - - - - - - - - - - - - - - - - 24.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
38 Steel truss Erection Rmt 24.00 0.00 0.00 0.00 - - - - - - - - - - - - - - - - 24.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
39 Deck Slab Rmt 24.00 0.00 0.00 0.00 - - - - - - - - - - - - - - - - 24.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -