Select Yozna: Select all Deselect all Select NABARD Running
# Component Name Unit TOTAL First Phase New Road (Stage I & II) Briddle Road Reconstruction Motor Bridge Briddle Bridge Building New Road (Stage I) New Road (Stage II) Other First Phase Bridge
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
Remaining
Target
Achivement
Total Achivement
1 do not use KM 3.00 2.00 2.00 2.00 - - - - - - - - - - - - - - - - - - - - - - - - - - - - 3.000 2.000 2.000 2.000 - - - - - - - - - - - -
2 PART 2 KM 381.84 86.70 56.28 170.48 2.000 2.000 1.800 1.800 287.355 57.720 37.840 129.170 5.000 1.000 0.000 0.000 54.970 8.700 4.550 24.025 0.000 0.000 0.000 0.000 - - - - - - - - 1.900 0.000 0.000 0.500 20.275 17.275 12.085 14.985 10.340 0.000 0.000 0.000 - - - -
3 P2 KM 0.00 0.00 0.00 0.00 - - - - - - - - - - - - 0.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
4 BM KM 14.68 11.68 7.68 7.68 - - - - - - - - - - - - 14.675 11.675 7.675 7.675 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
5 Bridge No 20.00 12.00 3.65 3.65 1.000 1.000 0.650 0.650 5.000 1.000 1.000 1.000 - - - - - - - - 8.000 8.000 2.000 2.000 4.000 2.000 0.000 0.000 - - - - - - - - - - - - - - - - 2.000 0.000 0.000 0.000
6 Stage KM 102.40 9.90 3.00 14.85 93.900 8.900 1.000 12.850 - - - - - - - - 3.000 0.000 1.000 1.000 - - - - - - - - 1.000 1.000 1.000 1.000 - - - - 2.500 0.000 0.000 0.000 - - - - 2.000 0.000 0.000 0.000
7 New Construction Hill side Cutting Km 559.73 266.48 185.81 403.20 15.400 8.500 4.850 4.850 247.930 44.820 33.120 120.155 - - - - 1.500 1.000 1.000 6.800 - - - - - - - - - - - - 264.900 194.460 132.515 250.915 30.000 17.700 14.320 20.480 - - - - - - - -
8 Widening Improvement Hill side Cutting Km 24.10 20.10 14.00 14.00 - - - - - - - - - - - - 24.100 20.100 14.000 14.000 - - - - - - - - - - - - 0.000 0.000 0.000 0.000 - - - - - - - - - - - -
9 Embankment Km 23.75 13.20 14.12 14.12 - - - - - - - - - - - - 1.800 1.180 1.000 1.000 - - - - - - - - - - - - - - - - 21.953 12.023 13.123 13.123 - - - - - - - -
10 Retaining Wall Rmt 963.23 866.73 566.73 566.73 - - - - 400.000 400.000 150.000 150.000 - - - - 563.230 466.730 416.730 416.730 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
11 Brest Wall Rmt 800.00 800.00 750.00 750.00 - - - - - - - - - - - - 800.000 800.000 750.000 750.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
12 Sub Base G1 Km 230.24 144.36 121.75 143.64 - - - - 7.260 7.260 7.080 7.905 - - - - 165.548 98.403 86.308 101.808 - - - - - - - - - - - - - - - - 57.431 38.696 28.363 33.923 - - - - - - - -
13 Sub Base GSB Km 37.71 17.15 18.69 19.19 - - - - - - - - - - - - 22.063 13.778 10.128 10.628 - - - - - - - - - - - - - - - - 15.645 3.370 8.565 8.565 - - - - - - - -
14 Base Course G2 Km 280.29 167.16 132.25 179.18 - - - - - - - - - - - - 217.316 130.901 108.536 152.506 - - - - - - - - - - - - - - - - 62.978 36.263 23.715 26.675 - - - - - - - -
15 Base Course G3 Km 381.65 241.52 191.51 262.51 - - - - 1.670 1.670 0.920 2.290 - - - - 306.379 196.094 158.464 224.834 - - - - - - - - - - - - - - - - 73.598 43.753 32.125 35.385 - - - - - - - -
16 DBM Km 14.97 6.65 5.57 7.07 - - - - - - - - - - - - 14.970 6.650 5.570 7.070 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
17 BM Km 78.12 55.94 30.99 35.54 - - - - - - - - - - - - 67.065 44.885 20.645 25.195 - - - - - - - - - - - - - - - - 0.710 0.710 0.000 0.000 10.340 10.340 10.340 10.340 - - - -
18 SDBC Km 144.60 112.30 59.66 83.76 - - - - - - - - - - - - 130.912 98.612 58.625 82.725 - - - - - - - - - - - - - - - - 2.030 2.030 1.030 1.030 11.660 11.660 0.000 0.000 - - - -
19 BC Km 66.36 54.36 37.99 37.99 - - - - - - - - - - - - 46.715 34.720 20.045 20.045 - - - - - - - - - - - - - - - - - - - - 19.640 19.640 17.940 17.940 - - - -
20 PC Km 523.15 356.98 320.68 393.57 - - - - 8.640 6.640 7.920 8.920 - - - - 442.707 296.012 273.352 343.492 - - - - - - - - - - - - - - - - 71.799 54.324 39.411 41.161 - - - - - - - -
21 DLC PCC Km 7.61 0.54 0.54 0.54 - - - - - - - - - - - - 7.070 0.000 0.000 0.000 - - - - - - - - - - - - - - - - 0.540 0.540 0.540 0.540 - - - - - - - -
22 PQC Km 0.54 0.54 0.54 0.54 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 0.540 0.540 0.540 0.540 - - - - - - - -
23 Interlocking Tile Rmt 107,056.35 48,436.79 35,545.44 36,247.74 - - - - 3.440 3.440 3.150 505.100 - - - - 70,514.363 29,355.803 22,284.353 22,284.353 - - - - - - - - - - - - - - - - 36,538.550 19,077.550 13,257.940 13,458.290 - - - - - - - -
24 Scupper No 74.00 58.00 42.00 42.00 - - - - 23.000 23.000 21.000 21.000 - - - - 51.000 35.000 21.000 21.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
25 Culverts No 1.00 1.00 1.00 1.00 - - - - - - - - - - - - 1.000 1.000 1.000 1.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
26 Cause Way No 29.00 3.00 1.00 1.00 - - - - - - - - - - - - 29.000 3.000 1.000 1.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
27 Unlined Drain Rmt 2,469.50 401.50 0.00 0.00 - - - - - - - - - - - - 2,469.500 401.500 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
28 Lined Drain Rmt 8,750.00 7,440.00 5,000.00 5,000.00 - - - - - - - - - - - - 8,240.000 7,440.000 5,000.000 5,000.000 - - - - - - - - - - - - - - - - - - - - 510.000 0.000 0.000 0.000 - - - -
29 Crash Barrier Rmt 3,925.00 0.00 0.00 0.00 - - - - - - - - - - - - 3,925.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
30 Parapet No 161.00 41.00 0.00 0.00 - - - - - - - - - - - - 161.000 41.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
31 Delineators Rmt 450.00 0.00 0.00 0.00 - - - - - - - - - - - - 450.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
32 Sign Board No 28.00 10.00 0.00 0.00 - - - - - - - - - - - - 28.000 10.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - - - - - -
33 Abutments LHS No 1.00 1.00 0.00 0.00 - - - - - - - - - - - - - - - - 1.000 1.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
34 Abutments RHS No 1.00 1.00 0.00 0.00 - - - - - - - - - - - - - - - - 1.000 1.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
35 Bearings No 6.00 0.00 0.00 0.00 - - - - - - - - - - - - - - - - 6.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
36 Solid Slab Rmt 0.00 0.00 0.00 0.00 - - - - - - - - - - - - - - - - 0.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
37 Girders Rmt 90.00 90.00 0.00 0.00 - - - - - - - - - - - - - - - - 90.000 90.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
38 Steel truss Fabrication Rmt 30.00 30.00 0.00 0.00 - - - - - - - - - - - - - - - - 30.000 30.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
39 Steel truss Erection Rmt 30.00 30.00 0.00 0.00 - - - - - - - - - - - - - - - - 30.000 30.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
40 Deck Slab Rmt 30.00 0.00 0.00 0.00 - - - - - - - - - - - - - - - - 30.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
41 Approach Road Rmt 95.00 0.00 0.00 0.00 - - - - - - - - - - - - - - - - 95.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
42 wing and return wall Rmt 59.48 59.48 31.48 31.48 - - - - - - - - - - - - 31.480 31.480 31.480 31.480 28.000 28.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
43 wearing coat Rmt 30.00 0.00 0.00 0.00 - - - - - - - - - - - - - - - - 30.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -
44 Hand rails Crash Barriers Rmt 60.00 0.00 0.00 0.00 - - - - - - - - - - - - - - - - 60.000 0.000 0.000 0.000 - - - - - - - - - - - - - - - - - - - - - - - -