Infrastructure Damage Report : बड़ेथी इन्द्रा टिपरी मोटर मार्ग

1952 - निर्माण खण्ड उत्तरकाषी - Uttarkashi

4

Total Damage Spots

₹ 13.75 Lakhs

Total Estimated Cost

0

Completed

4

Pending

Status Wise Distribution
Cost Analysis
बड़ेथी इन्द्रा टिपरी मोटर मार्ग DivSegmentID:1952 Closure Report Closure Images

EE Office: निर्माण खण्ड उत्तरकाषी

District: Uttarkashi

Segment ID: 5094, EE Segment ID: 1952

Pics Count: 0

Damage Spots Details
Spot #1 - ID:3163 , near tipri, Chainage 1.500 - 1.530 , Damaged Length 0.03 KM

05-09-2025

Provisions (प्रावधानों की सूची)

R/W

Remark: this km is partially closed due to r/w damage

₹ 3.00 Lakh
Identified
Fund:Unknown
Spot #2 - ID:3170 , near tipri, Chainage 1.500 - 1.525 , Damaged Length 0.025 KM

05-09-2025

Provisions (प्रावधानों की सूची)

slip clearance work

Remark: these km are closed due to slip-km2, km3, km1, km7, km4

₹ 2.45 Lakh
Identified
Fund:Unknown
Spot #3 - ID:3158 , near tipri, Chainage 0.800 - 0.845 , Damaged Length 0.045 KM

07-09-2025

Provisions (प्रावधानों की सूची)

R/W

Remark: this km is partially closed due to r/w damage

₹ 8.00 Lakh
Identified
Fund:Unknown
Spot #4 - ID:4489 , Indra, Chainage 3.100 - 3.120 , Damaged Length 0.02 KM

08-09-2025

Provisions (प्रावधानों की सूची)

Slip Clearance

Remark: Road closed due to slip in km 4

₹ 0.30 Lakh
Identified
Fund:Unknown

All Damage Spots

ID Date Location Cost (₹ Lakh) Chainages Status Yojana
3163 05-09-2025 near tipri 3.00 1.500 to 1.530 0.03 Identified Not Decided
3170 05-09-2025 near tipri 2.45 1.500 to 1.525 0.025 Identified Not Decided
3158 07-09-2025 near tipri 8.00 0.800 to 0.845 0.045 Identified Not Decided
4489 08-09-2025 Indra 0.30 3.100 to 3.120 0.02 Identified Not Decided