1953 - निर्माण खण्ड उत्तरकाषी - Uttarkashi
Total Damage Spots
Total Estimated Cost
Completed
Pending
EE Office: निर्माण खण्ड उत्तरकाषी
District: Uttarkashi
Segment ID: 5095, EE Segment ID: 1953
Pics Count: 5
06-09-2025
scupper wall damage
Remark: Na
06-09-2025
R/W damage
Remark: Na
06-09-2025
r/w damage
Remark: Na
06-09-2025
b/w damage
Remark: Na
06-09-2025
R/W damage
Remark: Na
06-09-2025
R/W damage
Remark: Na
06-09-2025
R/W damage
Remark: Na
08-09-2025
slip clearance work.
Remark: road partially closed due to slip.
ID | Date | Location | Cost (₹ Lakh) | Chainages | Status | Yojana |
---|---|---|---|---|---|---|
2531 | 06-09-2025 | Badsi | 4.00 | 1.125 to 1.175 0.05 | Identified | Not Decided |
2537 | 06-09-2025 | Badsi | 4.00 | 2.550 to 2.700 0.15 | Identified | Not Decided |
2542 | 06-09-2025 | Badsi | 4.00 | 3.125 to 3.150 0.025 | Identified | Not Decided |
2549 | 06-09-2025 | Badsi | 4.00 | 4.150 to 4.325 0.175 | Identified | Not Decided |
2550 | 06-09-2025 | Badsi | 4.00 | 5.250 to 5.450 0.2 | Identified | Not Decided |
2555 | 06-09-2025 | Pujargaon | 4.00 | 7.325 to 7.450 0.125 | Identified | Not Decided |
2561 | 06-09-2025 | Katkhan gaon | 4.00 | 12.200 to 12.300 0.1 | Identified | Not Decided |
4512 | 08-09-2025 | near badsi | 0.50 | 6.200 to 6.250 0.05 | Identified | Not Decided |