2194 - अस्थाई खण्ड गौचर - Chamoli
Total Damage Spots
Total Estimated Cost
Completed
Pending
EE Office: अस्थाई खण्ड गौचर
District: Chamoli
Segment ID: 1755, EE Segment ID: 2194
Pics Count: 8
02-08-2025
RR Dry for Retaining Wall
Remark: This retaining wall is to make the motor road passable for traffic.
02-08-2025
RR Dry for Retaining Wall
Remark: This retaining wall is to make the motor road passable for traffic.
02-08-2025
RR Dry for Retaining Wall
Remark: This retaining wall is to make the motor road passable for traffic.
02-08-2025
Plum masonary and Gabbions for Retaining Wall
Remark: This retaining wall is to make the highway passable for traffic.
02-08-2025
RR Dry for Retaining Wall.
Remark: This Wall is necessary in this location.
13-07-2026
15-07-2026
16-07-2026
| ID | Date | Location | Cost (₹ Lakh) | Chainages | Status | Yojana |
|---|---|---|---|---|---|---|
| 1769 | 02-08-2025 | villge bichona | 2.00 | 0.100 to 0.112 0.012 | Identified | SRMD |
| 1773 | 02-08-2025 | Village Bichona | 2.50 | 2.250 to 2.265 0.015 | Identified | SRMD |
| 1779 | 02-08-2025 | village bichona | 1.00 | 2.850 to 2.859 0.0089999999999999 | Identified | SRMD |
| 1783 | 02-08-2025 | village bichona | 2.00 | 4.050 to 4.062 0.012 | Identified | SRMD |
| 1790 | 02-08-2025 | village bichona | 2.30 | 4.400 to 4.415 0.015 | Identified | SRMD |
| 7544 | 13-07-2026 | Village Pungaon | 7.50 | Identified | Not Decided | |
| 7543 | 15-07-2026 | Village Pungaon | 3.10 | Identified | Not Decided | |
| 7542 | 16-07-2026 | Village Pungaon | 2.00 | Identified | Not Decided |
Try adjusting your filters to see more results