4648 - निर्माण खण्ड श्रीनगर - Pauri
Total Damage Spots
Total Estimated Cost
Completed
Pending
EE Office: निर्माण खण्ड श्रीनगर
District: Pauri
Segment ID: 3704, EE Segment ID: 4648
Pics Count: 3
02-09-2025
Rwall Damaged/slip clearance
Remark: R/wall damaged
02-09-2025
Rwall Damaged/slip clearance
Remark: Rwall Damaged/slip clearance
02-09-2025
slip clearance
Remark: slip clearance
ID | Date | Location | Cost (₹ Lakh) | Chainages | Status | Yojana |
---|---|---|---|---|---|---|
1481 | 02-09-2025 | Gawana | 4.00 | 0.750 to 0.770 0.02 | Identified | Not Decided |
1484 | 02-09-2025 | Gawana | 6.00 | 0.980 to 1.000 0.02 | Identified | Not Decided |
1501 | 02-09-2025 | rampur Gawana | 0.15 | 0.050 to 0.075 0.025 | Identified | Not Decided |