Infrastructure Damage Report : चाक्यू-हिलोगी मोटर मार्ग।

4831 - निर्माण खण्ड दुगड्डा - Pauri

11

Total Damage Spots

₹ 27.85 Lakhs

Total Estimated Cost

0

Completed

11

Pending

Status Wise Distribution
Cost Analysis
चाक्यू-हिलोगी मोटर मार्ग। DivSegmentID:4831 Closure Report Closure Images

EE Office: निर्माण खण्ड दुगड्डा

District: Pauri

Segment ID: 3200, EE Segment ID: 4831

Pics Count: 11

Damage Spots Details
Spot #1 - ID:1254 , -, Chainage 2.2 - 2.400 , Damaged Length 0.2 KM

25-08-2025

Provisions (प्रावधानों की सूची)

Excavation in foundation of retaining wall, cement plum concrete masonary, Hand packed stone filing, Random rubble stone masonry laid in dry

Remark: n

₹ 1.75 Lakh
Identified
Fund:Unknown
Spot #2 - ID:1255 , Sodkhet, Chainage 2.4 - 2.600 , Damaged Length 0.2 KM

25-08-2025

Provisions (प्रावधानों की सूची)

Excavation in foundation of retaining wall, cement plum concrete masonary, Hand packed stone filing, Random rubble stone masonry laid in dry

Remark: h

₹ 2.20 Lakh
Identified
Fund:Unknown
Spot #3 - ID:1256 , Sodkhet, Chainage 2.400 - 2.600 , Damaged Length 0.2 KM

25-08-2025

Provisions (प्रावधानों की सूची)

Excavation in foundation of retaining wall, cement plum concrete masonary, Hand packed stone filing, Random rubble stone masonry laid in dry

₹ 1.00 Lakh
Identified
Fund:Unknown
Spot #4 - ID:1257 , Hilogi, Chainage 4.00 - 4.200 , Damaged Length 0.2 KM

25-08-2025

Provisions (प्रावधानों की सूची)

Excavation in foundation of retaining wall, cement plum concrete masonary, Hand packed stone filing, Random rubble stone masonry laid in dry

Remark: o

₹ 3.50 Lakh
Identified
Fund:Unknown
Spot #5 - ID:1258 , -, Chainage 5.4 - 5.600 , Damaged Length 0.2 KM

25-08-2025

Provisions (प्रावधानों की सूची)

Excavation in foundation of retaining wall, cement plum concrete masonary, Hand packed stone filing, Random rubble stone masonry laid in dry

Remark: p

₹ 2.30 Lakh
Identified
Fund:Unknown
Spot #6 - ID:1259 , -, Chainage 5.600 - 5.800 , Damaged Length 0.2 KM

25-08-2025

Provisions (प्रावधानों की सूची)

Excavation in foundation of retaining wall, cement plum concrete masonary, Hand packed stone filing, Random rubble stone masonry laid in dry

₹ 2.70 Lakh
Identified
Fund:Unknown
Spot #7 - ID:1260 , -, Chainage 5.6 - 5.800 , Damaged Length 0.2 KM

25-08-2025

Provisions (प्रावधानों की सूची)

Excavation in foundation of retaining wall, cement plum concrete masonary, Hand packed stone filing, Random rubble stone masonry laid in dry

Remark: l

₹ 2.90 Lakh
Identified
Fund:Unknown
Spot #8 - ID:1261 , -, Chainage 5.8 - 6.000 , Damaged Length 0.2 KM

25-08-2025

Provisions (प्रावधानों की सूची)

Excavation in foundation of retaining wall, cement plum concrete masonary, Hand packed stone filing, Random rubble stone masonry laid in dry

Remark: j

₹ 2.80 Lakh
Identified
Fund:Unknown
Spot #9 - ID:1262 , -, Chainage 5.6 - 5.800 , Damaged Length 0.2 KM

25-08-2025

Provisions (प्रावधानों की सूची)

Excavation in foundation of retaining wall, cement plum concrete masonary, Hand packed stone filing, Random rubble stone masonry laid in dry

Remark: h

₹ 2.70 Lakh
Identified
Fund:Unknown
Spot #10 - ID:1263 , -, Chainage 2.00 - 2.200 , Damaged Length 0.2 KM

25-08-2025

Provisions (प्रावधानों की सूची)

Excavation in foundation of retaining wall, cement plum concrete masonary, Hand packed stone filing, Random rubble stone masonry laid in dry

Remark: h

₹ 2.50 Lakh
Identified
Fund:Unknown
Spot #11 - ID:1273 , -, Chainage 1.00 - 1.200 , Damaged Length 0.2 KM

25-08-2025

Provisions (प्रावधानों की सूची)

Excavation in foundation of retaining wall, cement plum concrete masonary, Hand packed stone filing, Random rubble stone masonry laid in dry

Remark: p

₹ 3.50 Lakh
Identified
Fund:Unknown

All Damage Spots

ID Date Location Cost (₹ Lakh) Chainages Status Yojana
1254 25-08-2025 - 1.75 2.2 to 2.400 0.2 Identified Not Decided
1255 25-08-2025 Sodkhet 2.20 2.4 to 2.600 0.2 Identified Not Decided
1256 25-08-2025 Sodkhet 1.00 2.400 to 2.600 0.2 Identified Not Decided
1257 25-08-2025 Hilogi 3.50 4.00 to 4.200 0.2 Identified Not Decided
1258 25-08-2025 - 2.30 5.4 to 5.600 0.2 Identified Not Decided
1259 25-08-2025 - 2.70 5.600 to 5.800 0.2 Identified Not Decided
1260 25-08-2025 - 2.90 5.6 to 5.800 0.2 Identified Not Decided
1261 25-08-2025 - 2.80 5.8 to 6.000 0.2 Identified Not Decided
1262 25-08-2025 - 2.70 5.6 to 5.800 0.2 Identified Not Decided
1263 25-08-2025 - 2.50 2.00 to 2.200 0.2 Identified Not Decided
1273 25-08-2025 - 3.50 1.00 to 1.200 0.2 Identified Not Decided