Infrastructure Damage Report : बसगांंव तवालेख मोटर मार्ग

497 - निर्माण खण्ड नैनीताल - Nanital

3

Total Damage Spots

₹ 11.00 Lakhs

Total Estimated Cost

0

Completed

3

Pending

Status Wise Distribution
Cost Analysis
बसगांंव तवालेख मोटर मार्ग DivSegmentID:497 Closure Report Closure Images

EE Office: निर्माण खण्ड नैनीताल

District: Nanital

Segment ID: 2702, EE Segment ID: 497

Pics Count: 5

Damage Spots Details
Spot #1 - ID:1327 , Basgaon, Chainage 1.850 - 1.865 , Damaged Length 0.015 KM

05-08-2025

Provisions (प्रावधानों की सूची)
  1. R wall Damage at Km 2 Hm 8-10 15*3.50

Remark: -

₹ 2.00 Lakh
Identified
Fund:Unknown
Spot #2 - ID:1329 , Basgaon, Chainage 2.180 - 2.222 , Damaged Length 0.042 KM

05-08-2025

Provisions (प्रावधानों की सूची)
  1. R wall & T Wall Damage at Km 3 Hm 0-2 13*3.50
  2. R wall & T Wall Damage at Km 3 Hm 0-2 9*3.0
  3. R wall & T Wall Damage at Km 3 Hm 0-2 20*3.0

Remark: -

₹ 5.50 Lakh
Identified
Fund:Unknown
Spot #3 - ID:1330 , Basgaon, Chainage 3.150 - 3.180 , Damaged Length 0.03 KM

05-08-2025

Provisions (प्रावधानों की सूची)
  1. R wall & T Wall Damage at Km 4 Hm 0-2 13*3.50
  2. R wall & T Wall Damage at Km 4 Hm 0-2 17*3.0

Remark: -

₹ 3.50 Lakh
Identified
Fund:Unknown

All Damage Spots

ID Date Location Cost (₹ Lakh) Chainages Status Yojana
1327 05-08-2025 Basgaon 2.00 1.850 to 1.865 0.015 Identified Not Decided
1329 05-08-2025 Basgaon 5.50 2.180 to 2.222 0.042 Identified Not Decided
1330 05-08-2025 Basgaon 3.50 3.150 to 3.180 0.03 Identified Not Decided