5431 - प्रान्तीय खण्ड बागेष्वर - Bageshwar
Total Damage Spots
Total Estimated Cost
Completed
Pending
EE Office: प्रान्तीय खण्ड बागेष्वर
District: Bageshwar
Segment ID: 24, EE Segment ID: 5431
Pics Count: 15
23-07-2025
R/wall & gabians
Remark: safety work for houses in hill side due to heavy rainfall and landslide
17-08-2025
Remark: safety work for hill side damage due to landslide
17-08-2025
gabians slip clearance kc drain plum concrete
Remark: safety work for hill side due to land slide
23-08-2025
R/wall and drain
Remark: retaining wall damage due to heavy rainfall
25-08-2025
abutment, pcc, HP filling and toe wall for damaged scupper
Remark: scupper damage due to heavy rainfall
28-08-2025
Toe wall, pcc grade m10, grade m20, abutments, hp filling and weep holes for damaged scupper
Remark: Slab and bed blocks are safe
05-09-2025
PCC 1:3:6 PCC 1:2:4 RR Dry RR 1:6 Steel Reinforcement M25
Remark: scupper damaged at km 1 hm 0-2 due to heavy rainfall
ID | Date | Location | Cost (₹ Lakh) | Chainages | Status | Yojana |
---|---|---|---|---|---|---|
171 | 23-07-2025 | doba | 4.50 | 15 to 15.200 0.2 | Estimation Done | SDMF |
165 | 17-08-2025 | doba | 8.50 | 12.160 to 12.195 0.035 | Estimation Done | SRMD |
168 | 17-08-2025 | bijauri | 7.50 | 5.530 to 5.560 0.029999999999999 | Estimation Done | SRMD |
170 | 23-08-2025 | dhari | 4.10 | 9.315 to 9.336 0.021000000000001 | Estimation Done | SDMF |
164 | 25-08-2025 | doba | 1.00 | 12.210 to 12.215 0.004999999999999 | Estimation Done | SRMD |
5759 | 28-08-2025 | Doba | 1.80 | Identified | Not Decided | |
1956 | 05-09-2025 | nadigaon | 6.00 | 0.150 to 0.175 0.025 | Identified | Not Decided |