5655 - अस्थाई खण्ड थत्यूड़ - Tehri
Total Damage Spots
Total Estimated Cost
Completed
Pending
EE Office: अस्थाई खण्ड थत्यूड़
District: Tehri
Segment ID: 167, EE Segment ID: 5655
Pics Count: 13
09-01-2025
Remark: NA
02-07-2025
Excavation Plum RR 1:6 RR dry etc
Remark: NA
02-07-2025
Excavation RR dry etc
Remark: NA
09-07-2025
RR DRY R/wall size (15x3.00)mtr
Remark: PROTECTION WORK
20-07-2025
Excavation RR 1:6 RR dry etc
Remark: PROTECTION WORK
05-08-2025
Excavation Plum RR 1:6 RR dry etc
Remark: NA
05-08-2025
PLUM TOE WAKK & RR DRY R/WALL
Remark: PROTECTION WORK
18-08-2025
Excavation Plum RR 1:6 RR dry etc
Remark: PROTECTION WORK
20-08-2025
excavation, RR 1:6, RR DRY, PLUM TOE WALL
Remark: PROTECTION WORK
22-08-2025
Excavation RR 1:6 RR dry etc
Remark: PROTECTION WORK
22-08-2025
Excavation Plum RR 1:6 RR dry etc
Remark: PROTECTION WORK
12-09-2025
Plum toe wall & Bended retaining wall
Remark: NA
12-09-2025
plum masonary toe wall & bended retaining wall
Remark: Right Km 23 (22.100 to 22.110)
| ID | Date | Location | Cost (₹ Lakh) | Chainages | Status | Yojana |
|---|---|---|---|---|---|---|
| 1875 | 09-01-2025 | Mason village | 1.80 | 7.900 to 7.915 0.015 | Estimation Done | SDRF |
| 601 | 02-07-2025 | Near Degree Collage | 10.00 | 1.150 to 1.180 0.03 | Estimation Done | SRMD |
| 604 | 02-07-2025 | Near Degree Collage | 3.74 | 1.210 to 1.250 0.04 | Estimation Done | SRMD |
| 3584 | 09-07-2025 | AINDI MARKET | 1.50 | 28.850 to 28.865 0.014999999999997 | Estimation Done | SRMD |
| 605 | 20-07-2025 | Aindi | 2.40 | 28.230 to 28.245 0.015000000000001 | Estimation Done | SDRF |
| 600 | 05-08-2025 | Ghodakhuri | 4.00 | 12.100 to 12.110 0.0099999999999998 | Estimation Done | SDRF |
| 3421 | 05-08-2025 | NEGYANA | 2.00 | 17.750 to 17.760 0.010000000000002 | Estimation Done | SRMD |
| 599 | 18-08-2025 | Fafrog | 3.80 | 2.435 to 2.450 0.015 | Estimation Done | SDRF |
| 3348 | 20-08-2025 | JHANGERI | 3.00 | 20.920 to 20.935 0.014999999999997 | Estimation Done | SRMD |
| 606 | 22-08-2025 | Gharar | 7.58 | 21.500 to 21.530 0.030000000000001 | Estimation Done | SDRF |
| 609 | 22-08-2025 | Gharara | 6.00 | 21.900 to 21.925 0.025000000000002 | Estimation Done | SDRF |
| 5117 | 12-09-2025 | Fafrog | 2.80 | 1.550 to 1.565 0.015 | Estimation Done | SDRF |
| 5884 | 12-09-2025 | Khatyud | 2.49 | 23.100 to 23.110 0.009999999999998 | Estimation Done | SRMD |
Try adjusting your filters to see more results