Infrastructure Damage Report : त्यूनी चकराता मसूरी चम्बा नई टिहरी जीरो ब्रिज मलेथा राष्ट्रीय राजमार्ग

5732 - NH Srinagar - Tehri

13

Total Damage Spots

₹ 130.07 Lakhs

Total Estimated Cost

0

Completed

13

Pending

Status Wise Distribution
Cost Analysis
त्यूनी चकराता मसूरी चम्बा नई टिहरी जीरो ब्रिज मलेथा राष्ट्रीय राजमार्ग DivSegmentID:5732 Closure Report Closure Images

EE Office: NH Srinagar

District: Tehri

Segment ID: 19, EE Segment ID: 5732

Pics Count: 22

Damage Spots Details
Spot #1 - ID:61 , Maletha 309.100

16-02-2025

Provisions (प्रावधानों की सूची)

Reconstruction of Retaining Wall is required.

Remark: Estimate Prepared.

₹ 5.63 Lakh
Identified
Fund:Unknown
Spot #2 - ID:1961 , Tehri 234.100

15-06-2025

Provisions (प्रावधानों की सूची)

Reconstruction of Wall is required

Remark: Estimate Sent

₹ 7.96 Lakh
Identified
Fund:Unknown
Spot #3 - ID:55 , Kuttha 239.900

26-07-2025

Provisions (प्रावधानों की सूची)

Reconstruction of Wall is required.

Remark: Estimate Prepared.

₹ 7.97 Lakh
Identified
Fund:Unknown
Spot #4 - ID:58 , Nandgaon 271.900

26-07-2025

Provisions (प्रावधानों की सूची)

Reconstruction of Drain and Catchpit is required.

Remark: Estimate Prepared.

₹ 3.33 Lakh
Identified
Fund:Unknown
Spot #5 - ID:1835 , Tehri to maletha 244.800

06-08-2025

Provisions (प्रावधानों की सूची)

Deployment of Machines

Remark: Estimate Sent

₹ 21.94 Lakh
Identified
Fund:Unknown
Spot #6 - ID:56 , Badkot 268.100

11-08-2025

Provisions (प्रावधानों की सूची)

Construction of Breast Wall is required.

Remark: Estimate Prepared.

₹ 13.65 Lakh
Identified
Fund:Unknown
Spot #7 - ID:57 , Cholgaon 269.900

11-08-2025

Provisions (प्रावधानों की सूची)

Construction of Breast Wall is required.

Remark: Estimate Prepared.

₹ 10.72 Lakh
Identified
Fund:Unknown
Spot #8 - ID:59 , gadoliya 275.300

11-08-2025

Provisions (प्रावधानों की सूची)

Construction of Breast Wall is required.

Remark: Estimate Prepared.

₹ 2.39 Lakh
Identified
Fund:Unknown
Spot #9 - ID:1807 , Amoli 292.900

11-08-2025

Provisions (प्रावधानों की सूची)

Construction of a wall is required.

Remark: Estimate sent.

₹ 5.97 Lakh
Estimation Done
Fund:Unknown
Spot #10 - ID:1978 , Tipri 262.900

18-08-2025

Provisions (प्रावधानों की सूची)

Reconstruction of the wall is required

Remark: Estimation Done

₹ 22.00 Lakh
Identified
Fund:Unknown
Spot #11 - ID:54 , Kuttha 240.300

19-08-2025

Provisions (प्रावधानों की सूची)

Reconstruction of Wall is required.

Remark: Estimate Prepared.

₹ 12.45 Lakh
Estimation Done
Fund:Unknown
Spot #12 - ID:60 , Malupani 300.300

20-08-2025

Provisions (प्रावधानों की सूची)

Construction of Breast Wall is required.

Remark: Estimate Prepared.

₹ 6.06 Lakh
Identified
Fund:Unknown
Spot #13 - ID:1994 , Uttad 264.650

04-09-2025

Provisions (प्रावधानों की सूची)

Protection work is required.

Remark: Estimate is being prepared.

₹ 10.00 Lakh
Identified
Fund:Unknown

All Damage Spots

ID Date Location Cost (₹) Status Yojana
61 16-02-2025 Maletha 5.63 Identified Not Decided
1961 15-06-2025 Tehri 7.96 Identified Not Decided
55 26-07-2025 Kuttha 7.97 Identified Not Decided
58 26-07-2025 Nandgaon 3.33 Identified Not Decided
1835 06-08-2025 Tehri to maletha 21.94 Identified Not Decided
56 11-08-2025 Badkot 13.65 Identified Not Decided
57 11-08-2025 Cholgaon 10.72 Identified Not Decided
59 11-08-2025 gadoliya 2.39 Identified Not Decided
1807 11-08-2025 Amoli 5.97 Estimation Done Not Decided
1978 18-08-2025 Tipri 22.00 Identified Not Decided
54 19-08-2025 Kuttha 12.45 Estimation Done Not Decided
60 20-08-2025 Malupani 6.06 Identified Not Decided
1994 04-09-2025 Uttad 10.00 Identified Not Decided