Infrastructure Damage Report : सौधार पनुवाधोखन मोटर मार्ग ।

6008 - प्रान्तीय खण्ड रानीखेत - Almora

3

Total Damage Spots

₹ 9.64 Lakhs

Total Estimated Cost

0

Completed

3

Pending

Status Wise Distribution
Cost Analysis
सौधार पनुवाधोखन मोटर मार्ग । DivSegmentID:6008 Closure Report Closure Images

EE Office: प्रान्तीय खण्ड रानीखेत

District: Almora

Segment ID: 5879, EE Segment ID: 6008

Pics Count: 5

Damage Spots Details
Spot #1 - ID:6703 , 6008/ KM 2 HM 0-2 /Panwadokhan 2307, Chainage 1.020 - 1.027 , Damaged Length 0.007 KM

20-07-2026

Provisions (प्रावधानों की सूची)

Retaining Wall damage: 6.50 m x 3m

  1. Excavation: 10.4 cum @400.8 = 4168.32
  2. RR DRY : 21.45 cum @2157.2 = 46271.94
  3. HP Filling : 5.46 cum @1039 = 5672.94
  4. Total : 56113.2 +18% GST (10100.376) = 66213.58

KM 2 HM 0-2 R/wall Detail of Measurement S.No. Particular (item of work) No Length Width H/D Quantity Unit 1 Mis 1-2 Excavation in foundation for retaining, breast walls etc, in all types of soils and rocks including all lead, lift and disposal of surplus material as per direction of engineer - in - charge, as per drawing and technical specifications Clause 305.1 of MORD Specifiction KM 2 HM 0-2 R/wall 1 X 1/3 6.50 1.60 3.00 10.40

							Total	10.40	cum

2 Mis 1-3 Random Rubble Stone Masonry laid Dry, in breast walls, retaining walls, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction KM 2 HM 0-2 R/wall 1 X 1 6.50 (0.6+1.6)/2 3.00 21.45 Total 21.45 cum 3 Mis 1-5 Hand Packed stone filling in back of wallls including cost of all materials,royality, T&P etc. complete as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) KM 2 HM 0-2 R/wall 1 X 1 6.50 (0+0.6)/2 2.80 5.46 Total 5.46 cum

Remark: Estimation done in NON SDRF via 1958/4C Dated 08.09.2026

₹ 0.67 Lakh
Estimation Done
Fund:Unknown
Spot #2 - ID:6704 , 6008/ KM 2 HM 2-4 /Panwadokhan 2307, Chainage 1.250 - 1.257 , Damaged Length 0.007 KM

20-07-2026

Provisions (प्रावधानों की सूची)

Retaining Wall damage: 6.30 m x 3m

  1. Excavation: 10.08 cum @400.8 = 4040.064
  2. RR DRY : 20.79 cum @2157.2 = 44848.188
  3. HP Filling : 5.29 cum @1039 = 5496.31
  4. Total : 54384.562 +18% GST (9789.22116) = 64173.78

KM 2 HM 2-4 R/wall Detail of Measurement S.No. Particular (item of work) No Length Width H/D Quantity Unit 1 Mis 1-2 Excavation in foundation for retaining, breast walls etc, in all types of soils and rocks including all lead, lift and disposal of surplus material as per direction of engineer - in - charge, as per drawing and technical specifications Clause 305.1 of MORD Specifiction KM 2 HM 2-4 R/wall 1 X 1/3 6.30 1.60 3.00 10.08

							Total	10.08	cum

2 Mis 1-3 Random Rubble Stone Masonry laid Dry, in breast walls, retaining walls, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction KM 2 HM 2-4 R/wall 1 X 1 6.30 (0.6+1.6)/2 3.00 20.79 Total 20.79 cum 3 Mis 1-5 Hand Packed stone filling in back of wallls including cost of all materials,royality, T&P etc. complete as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) KM 2 HM 2-4 R/wall 1 X 1 6.30 (0+0.6)/2 2.80 5.29 Total 5.29 cum

Remark: Estimation done in NON SDRF via 1958/4C Dated 08.09.2026

₹ 0.65 Lakh
Estimation Done
Fund:Unknown
Spot #3 - ID:6705 , 6008/ KM 12 HM 0-2 / Bankota 2307, Chainage 11.050 - 11.064 , Damaged Length 0.014 KM

20-07-2026

Provisions (प्रावधानों की सूची)

Retaining Wall below Causeway damaged: 14 m x 8 m

  1. Excavation: 84.47 cum @400.8 = 33855.58
  2. RR 1:6 : 100.45 cum @3902.7 = 392026.22
  3. Plum : 63 cum @4096.7 = 258092.1
  4. HP Filling : 20.16 cum @1039 = 20946.24
  5. Total : 704920.14 +18% GST (126885.6252) = 831805.77

KM 12 HM 0-2 R/wall Detail of Measurement S.No. Particular (item of work) No Length Width H/D Quantity Unit 1 Mis 1-2 Excavation in foundation for retaining, breast walls etc, in all types of soils and rocks including all lead, lift and disposal of surplus material as per direction of engineer - in - charge, as per drawing and technical specifications Clause 305.1 of MORD Specifiction KM 12 HM 0-2 R/wall 1 X 1/3 14.00 2.27 5.00 52.97 KM 12 HM 0-2 Toe Wall 2 X 1/2 14.00 1.50 1.50 31.50 Total 84.47 cum 2 Mis 1-4 Random Rubble Stone Masonry laid in 1:6 cement and sand mortar, in breast walls, retaining walls, parapets, scuppers, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction KM 12 HM 0-2 R/wall 1 X 1 14.00 (0.6+2.27)/2 5.00 100.45 Total 100.45 cum 3 Mis 1-5 Hand Packed stone filling in back of wallls including cost of all materials,royality, T&P etc. complete as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) KM 12 HM 0-2 R/wall 1 X 1 14.00 (0+0.6)/2 4.80 20.16 Total 20.16 cum

4 Mis 2-1 Cement plum Masonry with 40% plum & 60% 1:3:6 cement concrete including supply of all material, labour, T&P etc. required for proper completion of the work. as per drawings and technical specifications Clause 802, 803, 1202 & 1203 of MORD Specifiction KM 12 HM 0-2 Toe Wall 2 X 1 14.00 1.50 1.50 63.00 Total 63.00

Remark: Estimation done in NON SDRF via 1958/4C Dated 08.09.2026

₹ 8.32 Lakh
Estimation Done
Fund:Unknown

All Damage Spots

ID Date Location Cost (₹ Lakh) Chainages Status Yojana
6703 20-07-2026 6008/ KM 2 HM 0-2 /Panwadokhan 2307 0.67 1.020 to 1.027 0.0069999999999999 Estimation Done SDRF
6704 20-07-2026 6008/ KM 2 HM 2-4 /Panwadokhan 2307 0.65 1.250 to 1.257 0.0069999999999999 Estimation Done SDRF
6705 20-07-2026 6008/ KM 12 HM 0-2 / Bankota 2307 8.32 11.050 to 11.064 0.013999999999999 Estimation Done SDRF