Infrastructure Damage Report : मूलाकोट काण्डे भुइंया मोटर मार्ग

6117 - निर्माण खण्ड लोहाघाट - Champawat

6

Total Damage Spots

₹ 27.65 Lakhs

Total Estimated Cost

0

Completed

6

Pending

Status Wise Distribution
Cost Analysis
मूलाकोट काण्डे भुइंया मोटर मार्ग DivSegmentID:6117 Closure Report Closure Images

EE Office: निर्माण खण्ड लोहाघाट

District: Champawat

Segment ID: 5988, EE Segment ID: 6117

Pics Count: 10

Damage Spots Details
Spot #1 - ID:2401 , Mulakot, Chainage 0.500 - 0.520 , Damaged Length 0.02 KM

01-08-2025

Provisions (प्रावधानों की सूची)

1.Damage Scupper=1.80m=0.22lakh 2.Toe Wall(2 Layer) 17.90mX1.50m=2.48 Lakh 3.Dry Retaining wall 17.90mX3.30=1.60lakh

Remark: wall damage

₹ 4.30 Lakh
Identified
Fund:Unknown
Spot #2 - ID:2446 , Mulakot, Chainage 1.550 - 1.570 , Damaged Length 0.02 KM

01-08-2025

Provisions (प्रावधानों की सूची)

1.Dry Retaining wall 12.10mX2.70m=0.85lakh 2.Dry Retaining wall 9.40mX2.40m=0.65lakh

Remark: wall damage

₹ 1.50 Lakh
Identified
Fund:Unknown
Spot #3 - ID:2504 , Mulakot, Chainage 2.550 - 2.560 , Damaged Length 0.01 KM

01-08-2025

Provisions (प्रावधानों की सूची)

1.Toe wall(plum) 8.60mX1.50m=0.95 Lakh 2.Dry Retaining Wall 8.60mX3.00m=0.70 Lakh

Remark: wall damage

₹ 1.65 Lakh
Identified
Fund:Unknown
Spot #4 - ID:2482 , Mulakot, Chainage 2.100 - 2.110 , Damaged Length 0.01 KM

06-08-2025

Provisions (प्रावधानों की सूची)

1.Toe wall (Plum) 9.20 mX1.50m=1.00lakh 2.Dry Retaining wall 9.20mX3.00m=0.75lakh 3.Damage scupper 2.40m=0.25lakh

Remark: wall damage

₹ 2.00 Lakh
Identified
Fund:Unknown
Spot #5 - ID:2544 , Mulakot, Chainage 2.700 - 2.725 , Damaged Length 0.025 KM

06-08-2025

Provisions (प्रावधानों की सूची)
  1. Toe wall (2 layer plum) 24.90mX1.50m=5.30 Lakh
  2. Dry Reaining wall 24.90mX3.00m=1.95Lakh
  3. Toe wall (plum)14.00mX1.50m=0.85 Lakh
  4. Dry Reaining wall 14.00mX3.00m=1.10Lakh

Remark: wall damage

₹ 9.20 Lakh
Identified
Fund:Unknown
Spot #6 - ID:2563 , Kande, Chainage 5.700 - 5.730 , Damaged Length 0.03 KM

06-08-2025

Provisions (प्रावधानों की सूची)
  1. Toe wall (2 layer plum) 26.80mX1.50m= 6.00Lakh
  2. Dry Reaining wall 26.80mX3.30m=2.50 Lakh
  3. Damage sucpper 2.50 m=0.50Lakh

Remark: wall damage

₹ 9.00 Lakh
Identified
Fund:Unknown

All Damage Spots

ID Date Location Cost (₹ Lakh) Chainages Status Yojana
2401 01-08-2025 Mulakot 4.30 0.500 to 0.520 0.02 Identified Not Decided
2446 01-08-2025 Mulakot 1.50 1.550 to 1.570 0.02 Identified Not Decided
2504 01-08-2025 Mulakot 1.65 2.550 to 2.560 0.01 Identified Not Decided
2482 06-08-2025 Mulakot 2.00 2.100 to 2.110 0.0099999999999998 Identified Not Decided
2544 06-08-2025 Mulakot 9.20 2.700 to 2.725 0.025 Identified Not Decided
2563 06-08-2025 Kande 9.00 5.700 to 5.730 0.03 Identified Not Decided