6195 - निर्माण खण्ड बैजरो - Pauri
Total Damage Spots
Total Estimated Cost
Completed
Pending
EE Office: निर्माण खण्ड बैजरो
District: Pauri
Segment ID: 6066, EE Segment ID: 6195
Pics Count: 6
06-08-2025
Excavation PCC 1:3:6 HP stone filling RR 1:5 Stone masonary RCC M-25 R/wall dry weephole PCC M-20
Remark: Scupper damaged
06-08-2025
Excavation Gabions HP stone filling
Remark: R/wall damaged
06-08-2025
Excavation R/wall dry HP stone filling
Remark: R/wall damaged
06-08-2025
Excavation R/wall dry HP stone filling
Remark: R/wall damaged
15-09-2025
Excavation R/wall dry HP stone filling Gabions For Scupper (1)Excavation (2)PCC 1:3:6 (3)PCC 1:2:4 (4)RCC M-25 (5)RR 1:5 stone masonary (6)HYSD (7)Weephole (8)HP stone filling
Remark: Scupper damaged
| ID | Date | Location | Cost (₹ Lakh) | Chainages | Status | Yojana |
|---|---|---|---|---|---|---|
| 6404 | 06-08-2025 | Near sammaiya | 4.00 | Identified | SDRF | |
| 6405 | 06-08-2025 | Near daang | 1.00 | Identified | SDRF | |
| 6406 | 06-08-2025 | Near Basola | 1.50 | Identified | SDRF | |
| 6407 | 06-08-2025 | Near daang | 1.50 | Identified | SDRF | |
| 6301 | 15-09-2025 | NearBhainswara | 4.00 | 0.500 to 0.900 0.4 | Identified | SDRF |
Try adjusting your filters to see more results