Infrastructure Damage Report : काठ की नाव से आजोली तल्ली मोटर मार्ग

9720 - प्रान्तीय खण्ड रानीखेत - Almora

4

Total Damage Spots

₹ 41.01 Lakhs

Total Estimated Cost

0

Completed

4

Pending

Status Wise Distribution
Cost Analysis
काठ की नाव से आजोली तल्ली मोटर मार्ग DivSegmentID:9720 Closure Report Closure Images

EE Office: प्रान्तीय खण्ड रानीखेत

District: Almora

Segment ID: 9234, EE Segment ID: 9720

Pics Count: 8

Damage Spots Details
Spot #1 - ID:467 , 9720-KM 2 HM 8-10 Ajolimalli, Chainage 1.800 - 1.810 , Damaged Length 0.01 KM

21-08-2025

Provisions (प्रावधानों की सूची)

R/wall LxH=9.50 m x 4.50 m

Remark: Estimate has been forwarded via eDPR No. 7457 dated 23.09.2025

₹ 2.60 Lakh
Estimation Done
Fund:Unknown
Spot #2 - ID:541 , 9720 - KM 2 HM 8-10 AJOLIMALLI, Chainage 1.880 - 1.897 , Damaged Length 0.017 KM

21-08-2025

Provisions (प्रावधानों की सूची)

RWALL LxH=17 m x 6 m

Remark: Estimate has been forwarded via eDPR No. 7457 dated 23.09.2025

₹ 6.20 Lakh
Estimation Done
Fund:Unknown
Spot #3 - ID:543 , 9720-km5 HM4-6 ajoli talli, Chainage 4.500 - 4.530 , Damaged Length 0.03 KM

21-08-2025

Provisions (प्रावधानों की सूची)

RWALL LxH=33m x 5.5 m

Detail of Measurement S.No. Particular (item of work) No Length Width H/D Quantity Unit 1 Mis 1-2 Excavation in foundation for retaining, breast walls etc, in all types of soils and rocks including all lead, lift and disposal of surplus material as per direction of engineer - in - charge, as per drawing and technical specifications Clause 305.1 of MORD Specifiction KM HM R/wall 1 X 1/3 33.00 2.43 5.50 147.02

							Total	147.02	cum

2 Mis 1-3 Random Rubble Stone Masonry laid Dry, in breast walls, retaining walls, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction KM HM R/wall 1 X 10 2.64 (0.8+2.23)/2 4.30 171.98 Total 171.98 cum 3 Mis 1-4 Random Rubble Stone Masonry laid in 1:6 cement and sand mortar, in breast walls, retaining walls, parapets, scuppers, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction KM HM R/wall 1 X 1 33.00 (0.6+2.43)/2 5.50 274.97 (- RR DRY) -171.98 Net 102.99

							Total	102.99	

4 Mis 1-5 Hand Packed stone filling in back of wallls including cost of all materials,royality, T&P etc. complete as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) KM HM R/wall 1 X 1 33.00 (0+0.6)/2 5.00 49.50 Total 49.50 cum

Remark: New Retaining Wall Needed.

₹ 10.42 Lakh
Identified
Fund:Unknown
Spot #4 - ID:548 , 9720- KM 5 HM-4-6 AJOLITALLI, Chainage 4.550 - 4.619 , Damaged Length 0.069 KM

21-08-2025

Provisions (प्रावधानों की सूची)

RWALL LxH=69m x 5.5 m

Detail of Measurement S.No. Particular (item of work) No Length Width H/D Quantity Unit 1 Mis 1-2 Excavation in foundation for retaining, breast walls etc, in all types of soils and rocks including all lead, lift and disposal of surplus material as per direction of engineer - in - charge, as per drawing and technical specifications Clause 305.1 of MORD Specifiction KM HM R/wall 1 X 1/3 69.00 2.43 5.50 307.40

							Total	307.40	cum

2 Mis 1-3 Random Rubble Stone Masonry laid Dry, in breast walls, retaining walls, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction KM HM R/wall 1 X 22 2.51 (0.8+2.23)/2 4.30 359.73 Total 359.73 cum 3 Mis 1-4 Random Rubble Stone Masonry laid in 1:6 cement and sand mortar, in breast walls, retaining walls, parapets, scuppers, etc. including supply of all material, labour, T&P and royaltiies etc. complete as per drawing and technical specifications Clauses 702, 704, 1202 & 1203 of MORD Specifiction KM HM R/wall 1 X 1 69.00 (0.6+2.43)/2 5.50 574.94 (- RR DRY) -359.73 Net 215.21

							Total	215.21	

4 Mis 1-5 Hand Packed stone filling in back of wallls including cost of all materials,royality, T&P etc. complete as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) KM HM R/wall 1 X 1 69.00 (0+0.6)/2 5.00 103.50 Total 103.50 cum

Remark: New Retaining Wall Needed.

₹ 21.79 Lakh
Identified
Fund:Unknown

All Damage Spots

ID Date Location Cost (₹ Lakh) Chainages Status Yojana
467 21-08-2025 9720-KM 2 HM 8-10 Ajolimalli 2.60 1.800 to 1.810 0.01 Estimation Done SRMD
541 21-08-2025 9720 - KM 2 HM 8-10 AJOLIMALLI 6.20 1.880 to 1.897 0.017 Estimation Done SRMD
543 21-08-2025 9720-km5 HM4-6 ajoli talli 10.42 4.500 to 4.530 0.03 Identified Not Decided
548 21-08-2025 9720- KM 5 HM-4-6 AJOLITALLI 21.79 4.550 to 4.619 0.069 Identified Not Decided