कुई डुमलोट मोटर मार्ग (ID: 5053) , नि0ख0 पाबौ , Pauri

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 1 2026-07-10 14:12:38 2026-07-10 19:12:38 2026-07-10 16:18:46 2 hours 6 mins Opened Mr Ashok Dhyani ,Assistant Engineer Civil ,61004781 0.10 0.10 Slip/ Landslide Slip clearance - 48306
2 1 2026-07-28 10:04:20 2026-07-28 13:04:00 2026-07-28 13:18:34 3 hours 14 mins Opened Mr Ashok Dhyani ,Assistant Engineer Civil ,61004781 0.05 0.05 Slip/ Landslide Closed 30.099281000000 78.920723000000 56941
3 1 2026-08-01 07:10:48 2026-08-01 15:10:48 2026-08-01 11:55:02 4 hours 44 mins Opened Mr Ashok Dhyani ,Assistant Engineer Civil ,61004781 0.07 0.07 Slip/ Landslide Slip clearance - 59246
4 1 2026-09-27 08:46:35 2026-09-27 10:46:35 2026-09-27 18:14:46 9 hours 28 mins Opened Sourabh Dhoundiyal ,Assistant Engineer ,42270213M01497 0.04 0.04 Slip/ Landslide Road closed - 82093
5 1 2026-09-28 07:53:49 2026-09-28 14:53:00 2026-09-28 11:30:45 3 hours 36 mins Opened Sourabh Dhoundiyal ,Assistant Engineer ,42270213M01497 0.03 0.03 Slip/ Landslide Road closed - 82758
6 2 2026-07-14 09:01:28 2026-07-14 20:01:00 2026-07-14 16:50:39 7 hours 49 mins Opened Mr Ashok Dhyani ,Assistant Engineer Civil ,61004781 0.15 0.15 Slip/ Landslide Slip clearance - 50580
Total: 0.44 0.44

Current Road KM Closures (as on 27 Nov 2026)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic