हापला मशोली मोटर मार्ग से गुड़म मोटर मार्ग (ID: 11190) , PMGSY , Chamoli

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 7 2026-07-04 08:05:04 2026-07-05 05:05:00 2026-07-04 17:01:14 8 hours 56 mins Opened SANJAY KUMAR ,URRDA ,42270313M01933 0.15 3.00 Slip/ Landslide 30.412472000000 79.233036000000 45232
2 7 2026-09-05 08:32:18 2026-09-05 17:32:00 2026-09-05 20:40:01 12 hours 7 mins Opened SANJAY KUMAR ,URRDA ,42270313M01933 0.10 0.00 Slip/ Landslide - 75304
3 5 2026-07-20 07:47:09 2026-07-23 17:50:00 2026-07-23 15:39:31 3 days 7 hours Opened SANJAY KUMAR ,URRDA ,42270313M01933 0.10 5.00 Slip/ Landslide, Retaining Wall Damage - 52824
4 5 2026-08-19 08:32:49 2026-08-20 10:32:00 2026-08-20 09:17:48 1 days 0 hours Opened SANJAY KUMAR ,URRDA ,42270313M01933 0.10 2.50 Slip/ Landslide, Retaining Wall Damage - 67738
5 9 2026-08-19 08:34:21 2026-08-19 19:34:00 2026-08-20 12:37:52 1 days 4 hours Opened SANJAY KUMAR ,URRDA ,42270313M01933 0.10 2.50 Slip/ Landslide, Retaining Wall Damage - 67739
6 9 2026-09-05 08:33:56 2026-09-05 20:33:00 2026-09-05 20:40:19 12 hours 6 mins Opened SANJAY KUMAR ,URRDA ,42270313M01933 0.10 0.00 Slip/ Landslide - 75305
7 8 2026-09-10 08:29:29 2026-09-10 19:29:00 2026-09-10 19:31:23 11 hours 1 mins Opened SANJAY KUMAR ,URRDA ,42270313M01933 0.20 0.00 Slip/ Landslide - 78284
Total: 0.85 13.00

Current Road KM Closures (as on 24 Nov 2026)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic