उज्जवलपुर सेम धारकोट मोटर मार्ग (ID: 2144) , प्रान्तीय खण्ड कर्णप्रयाग , Chamoli

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 1 2026-07-27 12:43:26 2026-07-27 16:43:00 2026-07-27 17:08:44 4 hours 25 mins Opened Amit Chauhan ,AE 2024 ,42270213M01494 0.15 0.15 Slip/ Landslide 30.182714000000 79.222358000000 56424
2 1 2026-09-28 07:09:05 2026-09-28 16:09:00 2026-09-28 16:25:02 9 hours 15 mins Opened Amit Chauhan ,AE 2024 ,42270213M01494 0.50 5.00 Slip/ Landslide - 82777
3 1 2026-09-28 17:44:06 2026-09-28 21:44:00 2026-09-28 22:30:31 4 hours 46 mins Opened Amit Chauhan ,AE 2024 ,42270213M01494 0.30 2.00 Slip/ Landslide - 83252
4 1 2026-09-29 09:32:11 2026-09-29 14:32:00 2026-09-29 13:24:35 3 hours 52 mins Opened Amit Chauhan ,AE 2024 ,42270213M01494 0.35 5.00 Slip/ Landslide - 83443
5 3 2026-08-01 12:16:43 2026-08-01 16:16:00 2026-08-01 17:22:12 5 hours 5 mins Opened Amit Chauhan ,AE 2024 ,42270213M01494 0.07 0.07 Slip/ Landslide 30.182317000000 79.234024000000 59367
6 3 2026-09-18 11:25:23 2026-09-18 16:25:00 2026-09-18 15:44:15 4 hours 18 mins Opened Amit Chauhan ,AE 2024 ,42270213M01494 0.35 5.00 Slip/ Landslide - 80591
7 2 2026-09-11 10:55:10 2026-09-11 14:55:00 2026-09-11 15:12:01 4 hours 16 mins Opened Amit Chauhan ,AE 2024 ,42270213M01494 0.35 2.00 Slip/ Landslide - 78463
Total: 2.07 19.22

Current Road KM Closures (as on 20 Nov 2026)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic