नलगांव भटियाणा मोटर मार्ग (ID: 2171) , निर्माण खण्ड थराली , Chamoli

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng
1 9 2025-06-23 09:45:30 2025-06-23 14:45:00 2025-06-23 12:46:57 3 hours 1 mins Opened Babita ,AE ,42270213F01852 0.30 5.00 Slip/ Landslide, Retaining Wall Damage Partially closed multiple chainage -
2 5 2025-06-25 09:07:57 2025-06-25 12:07:00 2025-06-25 12:38:02 3 hours 30 mins Opened Babita ,AE ,42270213F01852 0.20 2.00 Slip/ Landslide Slip आने से मार्ग अवरुद्ध हो गया है -
3 5 2025-06-27 11:12:26 2025-06-27 16:12:26 2025-06-27 15:44:51 4 hours 32 mins Opened Babita ,AE ,42270213F01852 0.03 0.07 Slip/ Landslide Slip at multiple chainage -
4 4 2025-06-27 11:12:26 2025-06-27 16:12:26 2025-06-27 15:44:11 4 hours 31 mins Opened Babita ,AE ,42270213F01852 0.03 0.07 Slip/ Landslide Slip at multiple chainage -
5 6 2025-06-27 11:12:26 2025-06-27 16:12:26 2025-06-27 15:45:51 4 hours 33 mins Opened Babita ,AE ,42270213F01852 0.03 0.07 Slip/ Landslide Slip at multiple chainage -
6 6 2025-06-28 06:46:27 2025-06-28 12:46:27 6 hours 0 mins Babita ,AE ,42270213F01852 0.09 0.30 Slip/ Landslide Slip -
Total: 0.68 7.51

Current Road KM Closures (as on 28 Jun 2025)

KM Tentative Opening Date Status
6 2025-06-28 12:46:27 Closed
Road is closed at KM 6 (tentative: 2025-06-28 12:46:27).

Proposed to be open up to: Sat 28 Jun 2025 12:46 (5 hours 14 minutes 7 seconds from now from now)