विसातली कठुली मोटर मार्ग (ID: 2389) , प्रान्तीय खण्ड नई टिहरी , Tehri

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 4 2025-07-23 17:06:47 2025-07-23 18:06:00 2025-07-23 17:48:56 42 mins 9 secs Opened Gajendra Kumar ,AE ,61005352 0.03 0.00 Slip/ Landslide - 12207
2 2 2025-08-05 08:51:35 2025-08-05 11:51:00 2025-08-05 10:15:08 1 hours 23 mins Opened Gajendra Kumar ,AE ,61005352 0.08 5.00 Slip/ Landslide, Retaining Wall Damage - 15501
3 2 2025-08-21 09:19:20 2025-08-21 16:19:00 2025-08-21 17:42:10 8 hours 22 mins Opened Gajendra Kumar ,AE ,61005352 0.12 8.00 Slip/ Landslide, Retaining Wall Damage - 25551
4 3 2025-08-12 08:48:41 2025-08-12 10:48:00 2025-08-12 10:10:43 1 hours 22 mins Opened Gajendra Kumar ,AE ,61005352 0.12 8.00 Slip/ Landslide - 20244
Total: 0.35 21.00

Current Road KM Closures (as on 28 Aug 2025)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic