शिवपुरी देखला मोटर मार्ग (ID: 2518) , निर्माण खण्ड नरेन्द्रनगर , Tehri

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 9 2026-06-18 10:42:15 2026-06-18 17:45:00 2026-06-18 18:05:10 7 hours 22 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.08 0.00 Slip/ Landslide slip clearance - 43445
2 9 2026-07-14 08:24:19 2026-07-14 15:24:00 2026-07-14 15:29:15 7 hours 4 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.03 0.00 Slip/ Landslide Slip clearance - 50504
3 9 2026-07-28 07:45:36 2026-07-28 16:55:00 2026-07-28 16:55:38 9 hours 10 mins Opened Mr Satya Prakash ,Assistant Engineer Civil ,61006225 0.06 0.00 Slip/ Landslide मार्ग यातायात हेतु आंशिक बाधित है कार्यस्थल पर जेसीबी मशीन द्वारा मलवा/बोल्डरों को हटाये जाने का कार्य किया जा रहा है। - 56648
4 9 2026-08-16 10:16:30 2026-08-16 17:16:00 2026-08-16 17:20:46 7 hours 4 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 4.00 0.00 Slip/ Landslide भारी वर्षा होने के कारण मार्ग यातायात हेतु बाधित है कार्यस्थल पर जेसीबी मशीन द्वारा मलवा/बोल्डरों को हटाये जाने का कार्य किया जा रहा है। - 65655
5 9 2026-08-31 07:59:28 2026-08-31 17:30:00 2026-08-31 18:01:51 10 hours 2 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.10 0.00 Slip/ Landslide भारी वर्षा होने के कारण मार्ग यातायात हेतु बाधित है कार्यस्थल पर जेसीबी मशीन द्वारा मलवा/बोल्डरों को हटाये जाने का कार्य किया जा रहा है। - 71403
6 9 2026-09-05 07:57:18 2026-09-05 16:58:00 2026-09-05 17:02:01 9 hours 4 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.10 0.00 Slip/ Landslide वर्षा होने के कारण मार्ग यातायात हेतु बाधित है कार्यस्थल पर जेसीबी मशीन द्वारा मलवा/बोल्डरों को हटाये जाने का कार्य किया जा रहा है। - 75033
7 7 2026-06-18 10:42:59 2026-06-18 17:45:00 2026-06-18 18:05:01 7 hours 22 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.08 0.00 Slip/ Landslide slip clearance - 43446
8 7 2026-08-20 10:48:46 2026-08-20 14:48:46 2026-08-20 14:59:19 4 hours 10 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.06 0.00 Slip/ Landslide मार्ग यातायात हेतु बाधित है कार्यस्थल पर जेसीबी मशीन द्वारा मलवा/बोल्डरों को हटाये जाने का कार्य किया जा रहा है। - 67919
9 3 2026-07-09 09:27:06 2026-07-09 14:55:00 2026-07-09 15:23:55 5 hours 56 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.05 0.00 Slip/ Landslide Slip clearance - 46890
10 3 2026-07-20 07:10:23 2026-07-20 11:50:00 2026-07-20 11:51:05 4 hours 40 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.04 0.00 Slip/ Landslide Slip clearance - 52346
11 6 2026-07-09 09:27:43 2026-07-09 14:55:00 2026-07-09 15:24:08 5 hours 56 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.05 0.00 Slip/ Landslide Slip clearance - 46891
12 10 2026-07-09 09:28:24 2026-07-09 14:55:00 2026-07-09 15:24:18 5 hours 55 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.05 0.00 Slip/ Landslide Slip clearance - 46892
13 10 2026-07-14 08:24:54 2026-07-14 15:24:00 2026-07-14 15:29:21 7 hours 4 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.03 0.00 Slip/ Landslide Slip clearance - 50505
14 8 2026-07-14 08:23:39 2026-07-14 15:23:00 2026-07-14 15:29:08 7 hours 5 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.00 0.00 Slip/ Landslide Slip clearance - 50503
15 8 2026-08-29 10:09:27 2026-08-29 13:40:00 2026-08-29 13:43:22 3 hours 33 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.08 0.00 Slip/ Landslide भारी वर्षा होने के कारण मार्ग यातायात हेतु बाधित है कार्यस्थल पर जेसीबी मशीन द्वारा मलवा/बोल्डरों को हटाये जाने का कार्य किया जा रहा है। 30.163012000000 78.367705000000 70818
16 2 2026-07-20 07:09:49 2026-07-20 11:55:00 2026-07-20 11:50:38 4 hours 40 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.04 0.00 Slip/ Landslide Slip clearance - 52344
17 5 2026-08-31 07:58:52 2026-08-31 14:58:00 2026-08-31 18:01:43 10 hours 2 mins Opened Mr Ashwani Kumar Yadav ,Assistant Engineer Civil ,42008196 0.10 0.00 Slip/ Landslide भारी वर्षा होने के कारण मार्ग यातायात हेतु बाधित है कार्यस्थल पर जेसीबी मशीन द्वारा मलवा/बोल्डरों को हटाये जाने का कार्य किया जा रहा है। - 71402
Total: 4.95 0.00

Current Road KM Closures (as on 22 Nov 2026)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic