| 1 |
5 |
2026-09-03 10:40:39 |
2026-09-03 21:40:00
|
2026-09-03 21:24:26 |
10 hours 43 mins |
Opened |
Mr Arun Kumar ,Assistant Engineer Civil ,750011120 |
0.20 |
0.00 |
Slip/ Landslide
|
|
|
Nagni Point JCB working for slip clearance for entire road |
|
-
|
|
|
74021 |
| 2 |
4 |
2026-09-04 09:52:54 |
2026-09-04 18:52:54
|
2026-09-04 18:47:09 |
8 hours 54 mins |
Opened |
Mr Arun Kumar ,Assistant Engineer Civil ,750011120 |
0.25 |
0.00 |
Slip/ Landslide
|
|
|
Today Nagni point JCB running at Gunogi silogi m/r for slip clearance for entire road with tipper |
|
-
|
|
|
74591 |
| 3 |
4 |
2026-09-07 08:25:52 |
2026-09-07 19:25:00
|
2026-09-07 20:15:35 |
11 hours 49 mins |
Opened |
Mr Arun Kumar ,Assistant Engineer Civil ,750011120 |
0.13 |
0.00 |
Slip/ Landslide
|
|
|
Slip clearance work for entire road with nagni HQ JCB + tipper |
|
-
|
|
|
76316 |
| 4 |
2 |
2026-09-07 08:24:00 |
2026-09-07 19:25:00
|
2026-09-07 19:46:12 |
11 hours 22 mins |
Opened |
Mr Arun Kumar ,Assistant Engineer Civil ,750011120 |
0.13 |
0.00 |
Slip/ Landslide
|
|
|
Slip clearance work for entire road nagni HQ JCB with TIpper |
|
-
|
|
|
76313 |