# | KM | Closed On | Tentative Date | Opened On | Response Time | Open Type | Informed By | Initial cost | Restoration Cost | Damage Type | Location | Chainages | Remark | PiC | geo location | lat | lng | ID |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | 2 | 2025-08-06 08:46:57 | 2025-08-06 14:46:57 | 2025-08-06 09:23:36 | 36 mins 39 secs | Opened | Mr Anil Kumar ,Assistant Engineer Civil ,90004147 | 0.06 | 0.10 | Slip/ Landslide | - | 16259 | ||||||
2 | 2 | 2025-08-18 12:33:40 | 2025-08-18 17:33:40 | 2025-08-18 17:43:06 | 5 hours 9 mins | Opened | Mr Anil Kumar ,Assistant Engineer Civil ,90004147 | 0.10 | 5.00 | Slip/ Landslide, Retaining Wall Damage | - | 24179 | ||||||
Total: | 0.16 | 5.10 |
KM | Tentative Opening Date | Status |
---|
is opened for Traffic