मदनपुर-डाडामण्डी स्न्याखाल मोटर मार्ग। (ID: 4833) , निर्माण खण्ड दुगड्डा , Pauri

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 4 2026-06-29 08:19:18 2026-06-29 11:19:18 2026-06-29 10:03:56 1 hours 44 mins Opened Hari Singh Negi ,Junior Engineer Technical ,020019335 0.10 0.10 Slip/ Landslide - 43992
2 4 2026-07-05 06:38:59 2026-07-05 15:00:00 2026-07-05 14:36:44 7 hours 57 mins Opened Hari Singh Negi ,Junior Engineer Technical ,020019335 0.10 0.10 Slip/ Landslide - 45476
3 4 2026-07-24 09:13:34 2026-07-24 11:30:00 2026-07-24 11:30:52 2 hours 17 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.30 0.30 Slip/ Landslide - 55357
4 4 2026-07-30 08:28:07 2026-07-30 16:00:00 2026-07-30 15:57:15 7 hours 29 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.07 0.07 Slip/ Landslide - 58310
5 4 2026-08-14 10:53:19 2026-08-14 14:00:00 2026-08-14 13:53:48 3 hours 0 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.06 0.06 Slip/ Landslide - 64857
6 4 2026-08-29 10:33:21 2026-08-29 14:00:00 2026-08-29 14:52:56 4 hours 19 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.07 0.07 Slip/ Landslide - 70825
7 4 2026-09-02 12:07:59 2026-09-02 16:07:00 2026-09-02 17:00:30 4 hours 52 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.15 0.20 Slip/ Landslide - 73306
8 1 2026-07-02 06:54:53 2026-07-02 09:54:53 2026-07-02 10:54:32 3 hours 59 mins Opened Hari Singh Negi ,Junior Engineer Technical ,020019335 0.10 0.10 Slip/ Landslide - 44574
9 1 2026-07-10 08:38:22 2026-07-10 14:30:00 2026-07-10 15:14:26 6 hours 36 mins Opened Hari Singh Negi ,Junior Engineer Technical ,020019335 0.20 0.20 Slip/ Landslide - 47827
10 1 2026-07-11 08:58:44 2026-07-11 12:30:00 2026-07-11 13:00:49 4 hours 2 mins Opened Hari Singh Negi ,Junior Engineer Technical ,020019335 0.10 0.10 Slip/ Landslide - 48770
11 1 2026-07-30 02:55:56 2026-07-30 12:30:00 2026-07-30 11:12:09 8 hours 16 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.08 0.08 Slip/ Landslide - 58329
12 1 2026-08-17 07:34:01 2026-08-17 12:00:00 2026-08-17 13:15:49 5 hours 41 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.06 0.06 Slip/ Landslide - 65994
13 1 2026-08-19 08:13:27 2026-08-19 14:30:00 2026-08-19 15:31:24 7 hours 17 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.10 0.10 Slip/ Landslide - 67232
14 1 2026-09-07 11:06:28 2026-09-07 13:06:00 2026-09-07 13:54:03 2 hours 47 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.03 0.03 Slip/ Landslide - 76495
15 1 2026-09-27 11:03:05 2026-09-27 12:30:00 2026-09-27 13:20:24 2 hours 17 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.03 0.03 Slip/ Landslide - 82249
16 2 2026-07-05 07:37:21 2026-07-05 15:00:00 2026-07-05 15:03:59 7 hours 26 mins Opened Hari Singh Negi ,Junior Engineer Technical ,020019335 0.10 0.10 Slip/ Landslide - 45475
17 2 2026-07-10 08:38:55 2026-07-10 14:30:00 2026-07-10 15:19:38 6 hours 40 mins Opened Hari Singh Negi ,Junior Engineer Technical ,020019335 0.20 0.20 Slip/ Landslide - 47828
18 2 2026-07-13 08:13:35 2026-07-13 11:00:00 2026-07-13 13:00:33 4 hours 46 mins Opened Hari Singh Negi ,Junior Engineer Technical ,020019335 0.10 0.10 Slip/ Landslide - 50135
19 2 2026-08-06 09:23:14 2026-08-06 12:23:00 2026-08-06 15:05:34 5 hours 42 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.05 0.05 Slip/ Landslide - 61560
20 2 2026-08-07 11:11:04 2026-08-07 15:30:00 2026-08-07 16:12:03 5 hours 0 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.06 0.06 Slip/ Landslide - 62471
21 2 2026-08-17 07:35:38 2026-08-17 12:00:00 2026-08-17 13:19:36 5 hours 43 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.07 0.07 Slip/ Landslide - 65997
22 2 2026-08-19 08:15:54 2026-08-19 14:30:00 2026-08-19 15:31:56 7 hours 16 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.10 0.10 Slip/ Landslide - 67235
23 2 2026-09-02 12:05:50 2026-09-02 17:05:00 2026-09-02 14:49:35 2 hours 43 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.10 0.10 Slip/ Landslide - 73302
24 5 2026-07-23 13:30:12 2026-07-23 14:00:00 2026-07-23 14:40:48 1 hours 10 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.30 0.30 Slip/ Landslide - 54928
25 5 2026-07-24 09:15:15 2026-07-24 11:30:00 2026-07-24 11:30:28 2 hours 15 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.30 0.30 Slip/ Landslide - 55358
26 5 2026-08-29 10:35:26 2026-08-29 14:00:00 2026-08-29 14:51:46 4 hours 16 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.08 0.08 Slip/ Landslide - 70826
27 5 2026-09-02 12:10:02 2026-09-02 16:10:00 2026-09-02 14:32:58 2 hours 22 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.10 0.10 Slip/ Landslide - 73310
28 3 2026-09-03 08:54:12 2026-09-03 15:00:00 2026-09-03 14:52:29 5 hours 58 mins Opened Mr Vikash Bisht ,Junior Engineer Technical ,420010208 0.09 0.09 Slip/ Landslide - 73975
Total: 3.20 3.25

Current Road KM Closures (as on 20 Nov 2026)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic