बसड़ा बूंगा देवियोंखाल मोटर मार्ग (ID: 4899) , निर्माण खण्ड दुगड्डा , Pauri

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 4 2025-06-26 10:48:31 2025-06-26 15:48:00 2025-06-27 15:09:31 1 days 4 hours Opened Ms Aakansha Bahuguna ,Assistant Engineer Civil ,42270213F01372 0.10 0.10 Slip/ Landslide Partially closed ..at km 3 and 5 .the machine will take 6 hours as it has to travel a distance from headquarters 29.800000000000 78.800000000000 2086
2 4 2025-06-29 10:30:30 2025-06-29 13:30:30 2025-06-29 12:00:01 1 hours 29 mins Opened Ms Aakansha Bahuguna ,Assistant Engineer Civil ,42270213F01372 0.15 0.15 Slip/ Landslide Road closed 29.777700000000 78.839400000000 3387
3 3 2025-08-22 07:21:25 2025-08-22 12:00:00 2025-08-22 09:54:35 2 hours 33 mins Opened Ms Aakansha Bahuguna ,Assistant Engineer Civil ,42270213F01372 0.10 0.10 Slip/ Landslide road closed - 26004
4 5 2025-08-22 07:23:13 2025-08-22 12:00:00 2025-08-22 09:55:04 2 hours 31 mins Opened Ms Aakansha Bahuguna ,Assistant Engineer Civil ,42270213F01372 0.10 0.10 Slip/ Landslide road closed - 26005
Total: 0.45 0.45

Current Road KM Closures (as on 28 Aug 2025)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic