# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 2 2025-06-22 06:12:28 2025-06-22 17:12:28 2025-06-22 18:06:38 11 hours 54 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.15 0.60 Slip/ Landslide Road closed due to slip and boulders at many places - 1207
2 5 2025-06-23 07:33:55 2025-06-23 18:33:55 2025-06-23 18:09:44 10 hours 35 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.08 0.25 Slip/ Landslide Road closed at many places due to boulders and slip - 1318
3 5 2025-06-28 08:03:10 2025-06-28 18:03:10 2025-06-28 17:06:43 9 hours 3 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.08 0.10 Slip/ Landslide Road closed at different locations due to slip and boulders - 2751
4 5 2025-07-14 08:03:40 2025-07-14 18:03:40 2025-07-14 18:34:53 10 hours 31 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.15 0.15 Slip/ Landslide Road closed at different locations due to slip and boulders - 9324
5 5 2025-07-21 09:58:21 2025-07-21 12:58:00 2025-07-21 12:37:59 2 hours 39 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.03 0.03 Scupper/ Culvert Damage Road closed due to scupper damage - 11156
6 6 2025-06-23 07:33:55 2025-06-23 18:33:55 2025-06-23 17:39:27 10 hours 5 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.08 0.25 Slip/ Landslide Road closed at many places due to boulders and slip - 1319
7 4 2025-06-28 08:03:10 2025-06-28 18:03:10 2025-06-28 17:37:10 9 hours 34 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.08 0.10 Slip/ Landslide Road closed at different locations due to slip and boulders - 2750
8 4 2025-07-30 07:08:28 2025-07-30 13:08:28 2025-07-30 13:35:44 6 hours 27 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.09 0.09 Slip/ Landslide Road closed at different locations due to slip and boulders - 13874
Total: 0.74 1.57

Current Road KM Closures (as on 08 Aug 2025)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic