रिखाड धोबीघाट आमकुलाऊ पोखरसैंण नवासू दिवोली सीली तल्ला / मल्ला मोरोबैण्ड जोगीमढी मोटर मार्ग (ID: 4954) , निर्माण खण्ड बैजरो , Pauri

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 4 2025-06-26 06:45:00 2025-06-26 17:45:00 2025-06-26 18:47:10 12 hours 2 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.08 0.25 Slip/ Landslide Road closed at different locations due to slip and boulders - 2005
2 4 2025-06-28 07:58:00 2025-06-28 18:58:00 2025-06-28 17:38:49 9 hours 40 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.08 0.10 Slip/ Landslide Road closed at different locations due to slip and boulders - 2745
3 4 2025-07-03 10:12:04 2025-07-03 18:12:04 2025-07-03 17:14:47 7 hours 2 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.08 0.08 Slip/ Landslide Road closed at different locations due to slip and boulders - 5802
4 4 2025-07-09 10:23:22 2025-07-09 18:23:22 2025-07-09 17:28:16 7 hours 4 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.05 0.05 Slip/ Landslide Road closed at different locations due to slip and boulders - 7676
5 3 2025-06-26 06:45:00 2025-06-26 17:45:00 2025-06-26 19:17:40 12 hours 32 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.08 0.25 Slip/ Landslide Road closed at different locations due to slip and boulders - 2004
6 3 2025-07-03 10:12:04 2025-07-03 18:12:04 2025-07-03 17:54:23 7 hours 42 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.08 0.08 Slip/ Landslide Road closed at different locations due to slip and boulders - 5801
7 3 2025-07-08 09:33:51 2025-07-08 18:33:51 2025-07-08 20:10:36 10 hours 36 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.14 0.14 Slip/ Landslide Road closed at different locations due to slip and boulders - 7247
8 5 2025-06-27 06:53:44 2025-06-27 18:53:44 2025-06-27 18:25:44 11 hours 32 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.08 0.15 Slip/ Landslide Road closed at different locations due to slip and boulders - 2276
9 5 2025-06-28 07:58:00 2025-06-28 18:58:00 2025-06-28 16:57:56 8 hours 59 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.08 0.10 Slip/ Landslide Road closed at different locations due to slip and boulders - 2746
10 5 2025-07-09 10:23:22 2025-07-09 18:23:22 2025-07-09 18:08:43 7 hours 45 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.05 0.05 Slip/ Landslide Road closed at different locations due to slip and boulders - 7677
11 5 2025-07-10 08:36:18 2025-07-10 13:36:18 2025-07-10 10:19:51 1 hours 43 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.07 0.07 Slip/ Landslide Road closed at different locations due to slip and boulders - 8048
12 5 2025-07-11 06:51:06 2025-07-11 12:51:06 2025-07-11 19:30:26 12 hours 39 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.80 0.80 Slip/ Landslide Road closed due to slip and boulders in different locations - 8485
13 6 2025-06-27 06:53:44 2025-06-27 18:53:44 2025-06-27 17:45:18 10 hours 51 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.08 0.15 Slip/ Landslide Road closed at different locations due to slip and boulders - 2277
14 6 2025-07-18 06:55:31 2025-07-18 14:55:00 2025-07-18 10:32:03 3 hours 36 mins Partially opened Lalit Mohan Singh ,JE T ,SJE252 0.10 0.10 Slip/ Landslide Road closed at different locations due to slip and boulders - 10349
15 1 2025-07-12 06:25:12 2025-07-12 11:25:12 2025-07-12 09:22:20 2 hours 57 mins Opened Lalit Mohan Singh ,JE T ,SJE252 0.06 0.06 Slip/ Landslide Road closed at different locations due to slip and boulders - 8838
Total: 1.91 2.43

Current Road KM Closures (as on 18 Jul 2025)

KM Tentative Opening Date Status
6 2025-07-18 14:55:00 Partially Closed
Road is partially open at KM 6 (tentative: 2025-07-18 14:55:00).

Proposed to be open up to: Fri 18 Jul 2025 14:55 (1 hour 5 minutes 21 seconds from now from now)