कुवां कफनौल मोटर मार्ग (ID: 5611) , निर्माण खण्ड बड़कोट , Uttarkashi

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 31 2025-06-27 12:58:09 2025-06-27 18:58:09 2025-06-27 17:21:26 4 hours 23 mins Opened Anuj Singh ,Junior Engineer Technical ,42270313M01765 0.20 0.00 Slip/ Landslide JCB Deployed - 2362
2 31 2025-06-30 08:18:38 2025-06-30 14:18:38 2025-06-30 11:24:07 3 hours 5 mins Opened Anuj Singh ,Junior Engineer Technical ,42270313M01765 0.20 0.00 Slip/ Landslide JCB Deployed - 3950
3 29 2025-07-02 08:30:29 2025-07-02 15:30:29 2025-07-02 10:22:52 1 hours 52 mins Opened Anuj Singh ,Junior Engineer Technical ,42270313M01765 0.20 0.00 Slip/ Landslide JCB Deployed - 5363
4 30 2025-07-12 07:57:47 2025-07-12 14:57:00 2025-07-12 16:11:13 8 hours 13 mins Opened Anuj Singh ,Junior Engineer Technical ,42270313M01765 0.20 0.00 Slip/ Landslide As information given by JE, road is closed due to slip and heavy boulder, JCB deployed. 30.745602000000 78.169393000000 8959
5 11 2025-07-24 09:14:53 2025-07-24 11:14:53 2025-07-24 10:13:01 58 mins 8 secs Opened Tanuj Kamboj ,EE ,42270213M00021 0.20 0.50 Slip/ Landslide मोटर मार्ग खोलने का कार्य प्रगति पर। - 12293
6 17 2025-07-24 09:16:10 2025-07-24 11:16:10 2025-07-24 11:44:58 2 hours 28 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.20 0.50 Slip/ Landslide मोटर मार्ग खोलने का कार्य प्रगति पर। - 12294
7 19 2025-07-24 09:17:15 2025-07-24 11:17:15 2025-07-24 11:40:13 2 hours 22 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.25 0.60 Slip/ Landslide मोटर मार्ग खोलने का कार्य प्रगति पर। - 12297
8 19 2025-07-26 07:21:49 2025-07-26 18:21:49 2025-07-26 19:23:49 12 hours 2 mins Opened Mr Sitaram Dobhal ,Assistant Engineer Civil ,42270313M00316 0.15 0.00 Slip/ Landslide JCB Deployed - 13154
9 21 2025-07-24 09:18:49 2025-07-24 11:18:49 2025-07-24 11:45:28 2 hours 26 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.30 0.65 Slip/ Landslide मोटर मार्ग खोलने का कार्य प्रगति पर। - 12298
10 23 2025-07-24 09:19:56 2025-07-24 11:19:56 2025-07-24 11:45:45 2 hours 25 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.30 8.00 Retaining Wall Damage मोटर मार्ग खोलने का कार्य प्रगति पर। - 12299
11 18 2025-07-26 07:21:49 2025-07-26 18:21:49 2025-07-26 19:23:35 12 hours 1 mins Opened Mr Sitaram Dobhal ,Assistant Engineer Civil ,42270313M00316 0.15 0.00 Slip/ Landslide JCB Deployed - 13153
12 1 2025-08-04 15:17:58 2025-08-04 19:17:58 2025-08-04 19:21:52 4 hours 3 mins Opened Mr Sitaram Dobhal ,Assistant Engineer Civil ,42270313M00316 0.15 0.00 Slip/ Landslide JCB deployed - 15363
13 4 2025-08-06 10:27:51 2025-08-06 12:27:51 2025-08-06 16:01:44 5 hours 33 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.30 0.50 Slip/ Landslide मार्ग खोलने की कायवाही की जा रही है। - 16700
14 25 2025-08-06 18:20:52 2025-08-07 02:20:52 2025-08-07 15:25:29 21 hours 4 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.50 1.00 Slip/ Landslide मार्ग खोलने की कार्यवाही की जा रही है - 17382
Total: 3.30 11.75

Current Road KM Closures (as on 08 Aug 2025)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic