चोसला चिल मोटर मार्ग (ID: 6066) , निर्माण खण्ड अल्मोडा , Almora

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 5 2025-06-23 09:19:44 2025-06-23 17:19:44 2025-06-23 16:19:57 7 hours 0 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.04 0.00 Slip/ Landslide road ke kai sthano me mal;wa aane se road ansik roop se band thi jise kholane hetu JCB machine bheji gai hai . - 1386
2 5 2025-07-04 08:12:22 2025-07-04 17:12:22 2025-07-04 17:43:11 9 hours 30 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 0.00 Slip/ Landslide marg ke kai sthano me malwa aane se mar aansik roop se band hai .marg kholne hetu JCB machine bhej di gai hai. - 6280
3 5 2025-07-09 07:57:57 2025-07-09 16:57:57 2025-07-09 16:37:05 8 hours 39 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The road is partially closed due to the arrival of Malwa at many places on the road and the drains on the road have been blocked. Water is flowing on the road.JCB machine has been sent to open the route. - 7521
4 5 2025-07-19 09:02:31 2025-07-19 18:02:31 2025-07-19 17:10:36 8 hours 8 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The road is partially closed and the drains are completely blocked due to the occurrence of Manwa at many places on the route. JCB machine has been sent to open the route. - 10679
5 5 2025-07-21 06:30:34 2025-07-21 13:30:34 2025-07-21 15:40:17 9 hours 9 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.03 0.00 Slip/ Landslide Road closed at km 3,4,6,8,9 - 10971
6 5 2025-07-27 08:56:45 2025-07-27 17:56:45 2025-07-27 16:46:57 7 hours 50 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The road is partially closed due to landslides at many places and the drains are completely blocked. JCB has been sent to open the road and drains. - 13284
7 5 2025-08-06 08:26:54 2025-08-06 12:26:54 2025-08-06 17:27:33 9 hours 0 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.04 0.00 Slip/ Landslide Road closed due to slip at km 4,6,8 (km 6 critical point) - 16211
8 5 2025-08-11 14:40:56 2025-08-11 19:40:56 2025-08-11 19:33:16 4 hours 52 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.07 0.00 Slip/ Landslide, Sinking, Fludding Road closed at km 5,6,7 (km 6,7 is critical sliding and sinking point) - 19954
9 5 2025-08-12 07:26:44 2025-08-12 12:26:44 2025-08-12 15:10:27 7 hours 43 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 5.00 Slip/ Landslide, Washout, Sinking, Fludding Road closed at km 5,6,7,8 due to slip, sinking and fludding. Km 6,7 is critical point - 20142
10 5 2025-08-14 09:26:39 2025-08-14 15:26:39 2025-08-15 17:41:10 1 days 8 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 6.25 Slip/ Landslide, Washout Road closed at km 5,6,7,8 closed due to slip and km 6,7 is critical point. Road sinking at km 6,7. - 21509
11 5 2025-08-16 08:27:45 2025-08-16 13:27:45 2025-08-16 19:11:06 10 hours 43 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 5.00 Slip/ Landslide, Washout Road closed at km 5,6,7,8 (km 6,7 critical sinking point) - 22591
12 6 2025-06-23 09:19:44 2025-06-23 17:19:44 2025-06-23 16:20:02 7 hours 0 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.04 0.00 Slip/ Landslide road ke kai sthano me mal;wa aane se road ansik roop se band thi jise kholane hetu JCB machine bheji gai hai . - 1387
13 6 2025-07-04 08:12:22 2025-07-04 17:12:22 2025-07-04 17:43:17 9 hours 30 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 0.00 Slip/ Landslide marg ke kai sthano me malwa aane se mar aansik roop se band hai .marg kholne hetu JCB machine bhej di gai hai. - 6281
14 6 2025-07-09 07:57:57 2025-07-09 16:57:57 2025-07-09 16:37:14 8 hours 39 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The road is partially closed due to the arrival of Malwa at many places on the road and the drains on the road have been blocked. Water is flowing on the road.JCB machine has been sent to open the route. - 7522
15 6 2025-07-19 09:02:31 2025-07-19 18:02:31 2025-07-19 17:10:46 8 hours 8 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The road is partially closed and the drains are completely blocked due to the occurrence of Manwa at many places on the route. JCB machine has been sent to open the route. - 10680
16 6 2025-07-21 06:30:34 2025-07-21 13:30:34 2025-07-21 15:41:57 9 hours 11 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.03 0.00 Slip/ Landslide Road closed at km 3,4,6,8,9 - 10972
17 6 2025-07-27 08:56:45 2025-07-27 17:56:45 2025-07-27 16:48:00 7 hours 51 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The road is partially closed due to landslides at many places and the drains are completely blocked. JCB has been sent to open the road and drains. - 13285
18 6 2025-07-29 09:24:38 2025-07-29 14:24:00 2025-08-01 14:57:01 3 days 5 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.30 25.00 Slip/ Landslide, Fludding Road closed falling a tree km 6, km 6,7,8 closed due to land slide and malwa. - 13559
19 6 2025-08-06 08:26:54 2025-08-06 12:26:00 2025-08-08 10:09:07 2 days 1 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.10 25.00 Slip/ Landslide, Washout, Sinking Road closed due to slip at km 6,8 (km 6 critical point) km 6 60 m part of road washout and sinking. - 16212
20 6 2025-08-11 14:40:56 2025-08-11 19:40:56 2025-08-11 19:33:41 4 hours 52 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.07 0.00 Slip/ Landslide, Sinking, Fludding Road closed at km 5,6,7 (km 6,7 is critical sliding and sinking point) - 19955
21 6 2025-08-12 07:26:44 2025-08-12 12:26:44 2025-08-12 15:10:42 7 hours 43 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 5.00 Slip/ Landslide, Washout, Sinking, Fludding Road closed at km 5,6,7,8 due to slip, sinking and fludding. Km 6,7 is critical point - 20143
22 6 2025-08-14 09:26:39 2025-08-14 15:26:39 2025-08-15 17:41:30 1 days 8 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 6.25 Slip/ Landslide, Washout Road closed at km 5,6,7,8 closed due to slip and km 6,7 is critical point. Road sinking at km 6,7. - 21510
23 6 2025-08-16 08:27:45 2025-08-16 13:27:45 2025-08-16 19:11:27 10 hours 43 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 5.00 Slip/ Landslide, Washout Road closed at km 5,6,7,8 (km 6,7 critical sinking point) - 22592
24 6 2025-08-18 07:14:07 2025-08-18 12:14:07 2025-08-18 18:49:47 11 hours 35 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 6.25 Slip/ Landslide, Washout, Sinking Road closed at km 6,7,8,9 due to slip, land slide and sinking of road. - 23577
25 6 2025-08-21 09:36:30 2025-08-21 13:36:30 2025-08-21 16:58:59 7 hours 22 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 6.67 Slip/ Landslide, Sinking Road closed due to slip at km 6,7,8 - 25565
26 6 2025-08-23 08:14:52 2025-08-23 13:14:52 2025-08-24 13:23:16 1 days 5 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 8.33 Slip/ Landslide Road closed at km 6,7,8 due to slip - 26456
27 6 2025-08-27 07:52:06 2025-08-27 11:52:06 2025-08-27 16:25:31 8 hours 33 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 6.67 Slip/ Landslide, Washout, Sinking Road closed at km 6,7,8 due to slip and sinking of road. - 28217
28 7 2025-06-23 09:19:44 2025-06-23 17:19:44 2025-06-23 16:20:13 7 hours 0 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.04 0.00 Slip/ Landslide road ke kai sthano me mal;wa aane se road ansik roop se band thi jise kholane hetu JCB machine bheji gai hai . - 1388
29 7 2025-07-04 08:12:22 2025-07-04 17:12:22 2025-07-04 17:43:26 9 hours 31 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 0.00 Slip/ Landslide marg ke kai sthano me malwa aane se mar aansik roop se band hai .marg kholne hetu JCB machine bhej di gai hai. - 6282
30 7 2025-07-19 09:02:31 2025-07-19 18:02:31 2025-07-19 17:10:55 8 hours 8 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The road is partially closed and the drains are completely blocked due to the occurrence of Manwa at many places on the route. JCB machine has been sent to open the route. - 10681
31 7 2025-07-21 06:30:34 2025-07-21 13:30:34 2025-07-21 15:42:34 9 hours 12 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.03 0.00 Slip/ Landslide Road closed at km 3,4,6,8,9 - 10973
32 7 2025-07-27 08:50:17 2025-07-27 13:50:17 2025-07-27 16:48:39 7 hours 58 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.07 0.00 Scupper/ Culvert Damage, Fludding Road closed at km 7,8,9 due to slip and mud. - 13235
33 7 2025-07-29 09:24:38 2025-07-29 14:24:38 2025-08-06 17:30:14 8 days 8 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 0.00 Slip/ Landslide, Fludding Road closed falling a tree km 6, km 6,7,8 closed due to land slide and malwa. - 13560
34 7 2025-08-11 14:40:56 2025-08-11 19:40:56 2025-08-11 19:33:59 4 hours 53 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.07 0.00 Slip/ Landslide, Sinking, Fludding Road closed at km 5,6,7 (km 6,7 is critical sliding and sinking point) - 19956
35 7 2025-08-12 07:26:44 2025-08-12 12:26:44 2025-08-12 15:10:55 7 hours 44 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 5.00 Slip/ Landslide, Washout, Sinking, Fludding Road closed at km 5,6,7,8 due to slip, sinking and fludding. Km 6,7 is critical point - 20144
36 7 2025-08-14 09:26:39 2025-08-14 15:26:39 2025-08-15 17:41:45 1 days 8 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 6.25 Slip/ Landslide, Washout Road closed at km 5,6,7,8 closed due to slip and km 6,7 is critical point. Road sinking at km 6,7. - 21511
37 7 2025-08-16 08:27:45 2025-08-16 13:27:45 2025-08-16 19:11:47 10 hours 44 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 5.00 Slip/ Landslide, Washout Road closed at km 5,6,7,8 (km 6,7 critical sinking point) - 22593
38 7 2025-08-18 07:14:07 2025-08-18 12:14:07 2025-08-18 18:50:07 11 hours 36 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 6.25 Slip/ Landslide, Washout, Sinking Road closed at km 6,7,8,9 due to slip, land slide and sinking of road. - 23578
39 7 2025-08-21 09:36:30 2025-08-21 13:36:30 2025-08-21 16:59:20 7 hours 22 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 6.67 Slip/ Landslide, Sinking Road closed due to slip at km 6,7,8 - 25566
40 7 2025-08-23 08:14:52 2025-08-23 13:14:52 2025-08-24 13:27:53 1 days 5 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 8.33 Slip/ Landslide Road closed at km 6,7,8 due to slip - 26457
41 7 2025-08-27 07:52:06 2025-08-27 11:52:06 2025-08-27 16:26:09 8 hours 34 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 6.67 Slip/ Landslide, Washout, Sinking Road closed at km 6,7,8 due to slip and sinking of road. - 28218
42 8 2025-06-23 09:19:44 2025-06-23 17:19:44 2025-06-23 16:20:20 7 hours 0 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.04 0.00 Slip/ Landslide road ke kai sthano me mal;wa aane se road ansik roop se band thi jise kholane hetu JCB machine bheji gai hai . - 1389
43 8 2025-06-25 10:01:59 2025-06-25 16:01:59 2025-06-25 18:07:18 8 hours 5 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 0.21 Slip/ Landslide, Retaining Wall Damage Km 8,9,10,11 me slip aane se road closed. - 1728
44 8 2025-07-04 08:12:22 2025-07-04 17:12:22 2025-07-04 17:43:32 9 hours 31 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 0.00 Slip/ Landslide marg ke kai sthano me malwa aane se mar aansik roop se band hai .marg kholne hetu JCB machine bhej di gai hai. - 6283
45 8 2025-07-21 06:30:34 2025-07-21 13:30:34 2025-07-21 15:42:59 9 hours 12 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.03 0.00 Slip/ Landslide Road closed at km 3,4,6,8,9 - 10974
46 8 2025-07-27 08:50:17 2025-07-27 13:50:17 2025-07-27 16:49:15 7 hours 58 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.07 0.00 Scupper/ Culvert Damage, Fludding Road closed at km 7,8,9 due to slip and mud. - 13236
47 8 2025-07-29 09:24:38 2025-07-29 14:24:38 2025-08-01 14:58:55 3 days 5 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 0.00 Slip/ Landslide, Fludding Road closed falling a tree km 6, km 6,7,8 closed due to land slide and malwa. - 13561
48 8 2025-08-06 08:26:54 2025-08-06 12:26:54 2025-08-06 17:26:19 8 hours 59 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.04 0.00 Slip/ Landslide Road closed due to slip at km 4,6,8 (km 6 critical point) - 16213
49 8 2025-08-12 07:26:44 2025-08-12 12:26:44 2025-08-12 15:11:10 7 hours 44 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 5.00 Slip/ Landslide, Washout, Sinking, Fludding Road closed at km 5,6,7,8 due to slip, sinking and fludding. Km 6,7 is critical point - 20145
50 8 2025-08-14 09:26:39 2025-08-14 15:26:39 2025-08-15 17:42:02 1 days 8 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 6.25 Slip/ Landslide, Washout Road closed at km 5,6,7,8 closed due to slip and km 6,7 is critical point. Road sinking at km 6,7. - 21512
51 8 2025-08-16 08:27:45 2025-08-16 13:27:45 2025-08-16 19:12:05 10 hours 44 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 5.00 Slip/ Landslide, Washout Road closed at km 5,6,7,8 (km 6,7 critical sinking point) - 22594
52 8 2025-08-18 07:14:07 2025-08-18 12:14:07 2025-08-18 18:50:32 11 hours 36 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 6.25 Slip/ Landslide, Washout, Sinking Road closed at km 6,7,8,9 due to slip, land slide and sinking of road. - 23579
53 8 2025-08-21 09:36:30 2025-08-21 13:36:30 2025-08-21 16:59:38 7 hours 23 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 6.67 Slip/ Landslide, Sinking Road closed due to slip at km 6,7,8 - 25567
54 8 2025-08-23 08:14:52 2025-08-23 13:14:52 2025-08-24 13:37:56 1 days 5 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 8.33 Slip/ Landslide Road closed at km 6,7,8 due to slip - 26458
55 8 2025-08-27 07:52:06 2025-08-27 11:52:06 2025-08-27 16:25:50 8 hours 33 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 6.67 Slip/ Landslide, Washout, Sinking Road closed at km 6,7,8 due to slip and sinking of road. - 28219
56 9 2025-06-25 10:01:59 2025-06-25 16:01:59 2025-06-25 18:07:45 8 hours 5 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 0.21 Slip/ Landslide, Retaining Wall Damage Km 8,9,10,11 me slip aane se road closed. - 1729
57 9 2025-07-21 06:30:34 2025-07-21 13:30:34 2025-07-21 15:39:33 9 hours 8 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.03 0.00 Slip/ Landslide Road closed at km 3,4,6,8,9 - 10975
58 9 2025-07-27 08:50:17 2025-07-27 13:50:17 2025-07-27 16:47:43 7 hours 57 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.07 0.00 Scupper/ Culvert Damage, Fludding Road closed at km 7,8,9 due to slip and mud. - 13237
59 9 2025-07-29 09:24:38 2025-07-29 14:24:38 2025-08-01 14:56:07 3 days 5 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 0.00 Slip/ Landslide, Fludding Road closed falling a tree km 6, km 6,7,8 closed due to land slide and malwa. - 13562
60 9 2025-08-18 07:14:07 2025-08-18 12:14:07 2025-08-18 18:50:50 11 hours 36 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.06 6.25 Slip/ Landslide, Washout, Sinking Road closed at km 6,7,8,9 due to slip, land slide and sinking of road. - 23580
61 10 2025-06-25 10:01:59 2025-06-25 16:01:59 2025-06-25 18:08:08 8 hours 6 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 0.21 Slip/ Landslide, Retaining Wall Damage Km 8,9,10,11 me slip aane se road closed. - 1730
62 11 2025-06-25 10:01:59 2025-06-25 16:01:59 2025-06-25 18:08:34 8 hours 6 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.05 0.21 Slip/ Landslide, Retaining Wall Damage Km 8,9,10,11 me slip aane se road closed. - 1731
63 4 2025-07-09 07:57:57 2025-07-09 16:57:57 2025-07-09 16:36:55 8 hours 38 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The road is partially closed due to the arrival of Malwa at many places on the road and the drains on the road have been blocked. Water is flowing on the road.JCB machine has been sent to open the route. - 7520
64 4 2025-07-21 06:30:34 2025-07-21 13:30:34 2025-07-21 15:37:21 9 hours 6 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.03 0.00 Slip/ Landslide Road closed at km 3,4,6,8,9 - 10970
Total: 3.83 206.49

Current Road KM Closures (as on 28 Aug 2025)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic