# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 10 2025-06-28 15:12:35 2025-06-28 18:12:35 2025-06-28 20:02:16 4 hours 49 mins Opened Ajay Sah ,Drafsman ,370014825 0.08 0.00 Slip/ Landslide - 2942
2 10 2025-08-08 07:23:51 2025-08-08 14:00:00 2025-08-08 13:00:34 5 hours 36 mins Opened Ajay Sah ,Drafsman ,370014825 0.12 0.00 Slip/ Landslide - 18251
3 2 2025-08-05 12:45:46 2025-08-05 18:00:00 2025-08-05 17:15:30 4 hours 29 mins Opened Ajay Sah ,Drafsman ,370014825 0.15 0.00 Slip/ Landslide - 15660
4 2 2025-08-31 09:12:01 2025-08-31 13:00:00 2025-08-31 13:34:40 4 hours 22 mins Opened Ajay Sah ,Drafsman ,370014825 0.10 0.00 Slip/ Landslide - 30246
5 4 2025-09-13 09:35:30 2025-09-13 13:00:00 2025-09-13 11:36:16 2 hours 0 mins Opened Ajay Sah ,Drafsman ,370014825 0.12 0.00 Slip/ Landslide - 37398
Total: 0.57 0.00

Current Road KM Closures (as on 14 Oct 2025)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic