परखाल से डूंगरी मोटर मार्ग (ID: 8611) , निर्माण खण्ड थराली , Chamoli

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 3 2025-06-26 11:34:20 2025-06-26 15:34:20 2025-06-26 21:00:59 9 hours 26 mins Opened Babita ,AE ,42270213F01852 0.06 0.10 Slip/ Landslide Slip - 2081
2 3 2025-06-28 07:56:55 2025-06-28 12:56:55 2025-06-28 13:15:38 5 hours 18 mins Opened Babita ,AE ,42270213F01852 3.00 10.00 Slip/ Landslide, Scupper/ Culvert Damage Slip clearance recommended - 2590
3 4 2025-08-28 08:28:55 2025-08-28 14:28:00 5 hours 59 mins Babita ,AE ,42270213F01852 0.10 2.00 Slip/ Landslide - 28594
Total: 3.16 12.10

Current Road KM Closures (as on 28 Aug 2025)

KM Tentative Opening Date Status
4 2025-08-28 14:28:00 Closed
Road is closed at KM 4 (tentative: 2025-08-28 14:28:00).

Proposed to be open up to: Thu 28 Aug 2025 14:28 (1 hour 51 minutes 37 seconds from now from now)