बल्ली से मथाणा मोटर मार्ग (ID: 9105) , PMGSY , Pauri

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 4 2026-07-02 08:21:26 2026-07-03 08:21:00 2026-07-03 08:12:13 23 hours 50 mins Opened Vipin Saini ,URRDA ,DITPK4749A 0.30 5.00 Slip/ Landslide ROAD OPEN FOR TRAFFIC - 44590
2 4 2026-07-10 18:46:04 2026-07-11 09:46:00 2026-07-11 09:46:40 15 hours 0 mins Opened Vipin Saini ,URRDA ,DITPK4749A 0.30 2.00 Slip/ Landslide ROAD CLOSE FOR TRAFFIC 29.839623000000 78.494987000000 48499
3 4 2026-08-06 07:17:22 2026-08-06 17:17:22 2026-08-06 17:27:00 10 hours 9 mins Opened Vipin Saini ,URRDA ,DITPK4749A 0.25 0.00 Slip/ Landslide Road close traffic - 61452
4 5 2026-08-06 07:20:25 2026-08-06 17:20:25 2026-08-06 17:27:27 10 hours 7 mins Opened Vipin Saini ,URRDA ,DITPK4749A 0.25 0.00 Slip/ Landslide Road close traffic - 61456
Total: 1.10 7.00

Current Road KM Closures (as on 20 Nov 2026)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic