# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 6 2026-07-10 12:46:03 2026-07-10 13:46:03 2026-07-20 17:49:42 10 days 5 hours Opened Pankaj Kumar ,URRDA ,42270313M02489 0.05 0.00 Slip/ Landslide - 48163
2 6 2026-09-02 06:12:20 2026-09-02 13:12:00 2026-09-02 15:02:17 8 hours 49 mins Opened Pankaj Kumar ,URRDA ,42270313M02489 0.10 4.00 Slip/ Landslide - 73038
3 6 2026-09-03 06:11:40 2026-09-03 15:11:40 2026-09-03 13:27:45 7 hours 16 mins Opened Pankaj Kumar ,URRDA ,42270313M02489 0.06 4.00 Slip/ Landslide - 73920
4 9 2026-09-02 06:13:05 2026-09-02 13:13:05 2026-09-02 15:32:25 9 hours 19 mins Opened Pankaj Kumar ,URRDA ,42270313M02489 0.05 4.00 Slip/ Landslide - 73040
5 9 2026-09-03 06:12:55 2026-09-03 15:12:55 2026-09-03 13:59:30 7 hours 46 mins Opened Pankaj Kumar ,URRDA ,42270313M02489 0.04 3.00 Slip/ Landslide - 73922
6 9 2026-09-28 07:23:22 2026-09-28 16:23:00 2026-09-28 19:38:35 12 hours 15 mins Opened Pankaj Kumar ,URRDA ,42270313M02489 0.11 0.00 Slip/ Landslide - 82787
7 8 2026-09-03 06:12:15 2026-09-03 15:12:15 2026-09-03 13:39:10 7 hours 26 mins Opened Pankaj Kumar ,URRDA ,42270313M02489 0.06 4.00 Slip/ Landslide - 73921
8 1 2026-09-06 07:39:21 2026-09-06 18:39:00 2026-09-06 17:54:31 10 hours 15 mins Opened Pankaj Kumar ,URRDA ,42270313M02489 0.30 14.00 Slip/ Landslide - 75714
9 1 2026-09-16 07:40:14 2026-09-16 16:40:00 2026-09-16 19:03:37 11 hours 23 mins Opened Pankaj Kumar ,URRDA ,42270313M02489 0.20 8.00 Slip/ Landslide, Retaining Wall Damage 29.468576000000 79.523565000000 80111
10 1 2026-09-27 07:10:30 2026-09-27 17:10:00 2026-09-27 19:40:54 12 hours 30 mins Opened Pankaj Kumar ,URRDA ,42270313M02489 0.25 12.00 Slip/ Landslide - 82115
11 1 2026-09-28 07:22:46 2026-09-28 16:22:46 2026-09-28 18:38:25 11 hours 15 mins Opened Pankaj Kumar ,URRDA ,42270313M02489 0.11 0.00 Slip/ Landslide - 82786
Total: 1.33 53.00

Current Road KM Closures (as on 22 Nov 2026)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic