छाजा फटक्वालडुंगरा मोटर मार्ग (ID: 9589) , निर्माण खण्ड अल्मोडा , Almora

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 4 2025-06-25 10:30:13 2025-06-25 16:30:13 2025-06-26 19:44:58 1 days 9 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.03 0.03 Slip/ Landslide Partially closed - 1801
2 5 2025-06-25 10:30:13 2025-06-25 16:30:13 2025-06-26 19:46:02 1 days 9 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.03 0.03 Slip/ Landslide Partially closed - 1802
3 6 2025-06-25 10:30:13 2025-06-25 16:30:13 2025-06-26 19:45:44 1 days 9 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.03 0.03 Slip/ Landslide Partially closed - 1803
4 3 2025-06-25 10:30:13 2025-06-25 16:30:13 2025-06-26 19:44:25 1 days 9 hours Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.03 0.03 Slip/ Landslide Partially closed - 1800
5 9 2025-07-09 07:55:03 2025-07-09 16:55:03 2025-07-09 16:38:12 8 hours 43 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The road is partially closed due to the arrival of Malwa at many places on the road and the drains on the road have been blocked. Water is flowing on the road. JCB machine has been sent to open the route. - 7517
6 9 2025-07-14 09:28:06 2025-07-14 18:28:06 2025-07-14 17:49:37 8 hours 21 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The motor road is partially closed due to the arrival of slip.JCB machine has been sent to open the route. - 9477
7 8 2025-07-09 07:55:03 2025-07-09 16:55:03 2025-07-09 16:37:56 8 hours 42 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The road is partially closed due to the arrival of Malwa at many places on the road and the drains on the road have been blocked. Water is flowing on the road. JCB machine has been sent to open the route. - 7516
8 8 2025-07-14 09:28:06 2025-07-14 18:28:06 2025-07-14 17:48:57 8 hours 20 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The motor road is partially closed due to the arrival of slip.JCB machine has been sent to open the route. - 9476
9 7 2025-07-09 07:55:03 2025-07-09 16:55:03 2025-07-09 16:37:47 8 hours 42 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The road is partially closed due to the arrival of Malwa at many places on the road and the drains on the road have been blocked. Water is flowing on the road. JCB machine has been sent to open the route. - 7515
10 7 2025-07-14 09:28:06 2025-07-14 18:28:06 2025-07-14 17:48:31 8 hours 20 mins Opened Alok Kumar Oli ,Assistant Engineer Civil ,750022910 0.08 0.08 Slip/ Landslide The motor road is partially closed due to the arrival of slip.JCB machine has been sent to open the route. - 9475
Total: 0.60 0.60

Current Road KM Closures (as on 18 Jul 2025)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic