Work Profile Report [10W30]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0547/।।।- (2)/09-44 (प्रा0आ0) /08 दि0 11/2/09
TS Amount (lakhs) : 105 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
105.00
Resanction Cost :
105.00
Tentative Cost :
105.00
Exp. Upto Last Fy :
72.09
For CFY 2024-2025
Remaining :
32.91
Demand :
32.91
Allotment :
22.00
Exp in CFY :
7.68
Total Up to Date Exp :
79.76
Construction Started
Sanction on : 15 years 10 months ago
11 Feb 2009
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
50 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.00 कि0मी0 लम्बाई में पार्ट-।। का कार्य पूर्ण , शेष कार्य प्रगति पर है। -- as on 21-Dec-2024