Work Profile Report [10W358]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 909/XVIII-B-1/2023-4(63)/2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
56.39
Resanction Cost :
56.39
Tentative Cost :
56.39
Exp. Upto Last Fy :
28.19
For CFY 2025-2026
Remaining :
28.20
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
28.19
Construction Started
Sanction on : 1 year 11 months ago
04 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
55 %
Up to Date :
55 %
Tentative Completion date on : 9 months 1 week ago
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य का आगणन रू0 16476.83 लाख का गठित कर शासन को प्रेषित किया जा चुकाा है। -- as on 05-May-2025
Assets :