Administrative Approval Detail : संयुक्त सचिव, उत्तराखण्ड शासन, देहरादून का ई-फाईल संख्या 44081
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
166.43
Resanction Cost :
166.43
Tentative Cost :
166.43
Exp. Upto Last Fy :
20.89
For CFY 2024-2025
Remaining :
145.54
Demand :
111.00
Allotment :
0.00
Exp in CFY :
128.09
Total Up to Date Exp :
148.98
Construction Started
Sanction on : 1 year 1 month ago
03 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
2 %
Up to Date :
100 %
Tentative Completion date on : 5 days 4 hours from now
29 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पीसी का कार्य पूर्ण, कार्य नाबार्ड-30 के अन्तर्गत स्वीकृत हुआ है। -- as on 28-Oct-2024