Work Profile Report [10W7]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं063/।।। (2)/05-91 (प्रा0आ0)/05 दि0 16/01/06
TS Amount (lakhs) : 71.2 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
71.20
Resanction Cost :
71.20
Tentative Cost :
71.20
Exp. Upto Last Fy :
66.70
For CFY 2025-2026
Remaining :
4.50
Demand :
0.00
Allotment :
16.38
Exp in CFY :
0.00
Total Up to Date Exp :
66.70
Construction Started
Sanction on : 19 years 2 months ago
16 Jan 2006
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 5 days 8 hours ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 05-Mar-2025