Work Profile Report [11W1]
Fin Plan
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 595/।।।(2)/08-42(प्रा0आ0)/07 टी0सी0 दिनांक 20.03.2008
TS Amount (lakhs) : 12.25 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
12.25
Resanction Cost :
12.25
Tentative Cost :
12.25
Exp. Upto Last Fy :
9.52
For CFY 2024-2025
Remaining :
2.73
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
9.52
Work completed
Sanction on : 16 years 8 months ago
20 Mar 2008
Physical Progress:
At start of FY 2024-2025 :
76 %
Up to Date :
0 %
Tentative Completion date on : 14 years 9 months ago
31 Jan 2010
Actual Completion Date : 14 years 8 months ago
01 Mar 2010
Physical Linear Components
Remark
कार्य 12/2009 में पूर्ण।
Assets :