Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.4 | 2.4 | 2.4 | 0 |
Closed Work 11W457 :
Administrative Approval Detail : शासनादेश संख्या 430/।।। (2)/19-61 (एम0एल0ए0)/2017 टी0सी0 दिनांक 29.11.2019
TS Amount (lakhs) : 60.22 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.22
Resanction Cost :
60.22
Tentative Cost :
60.22
Exp. Upto Last Fy : 57.81
For CFY 2024-2025
Remaining : 2.41
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 57.81
Work completed
Physical Progress:
At start of FY 2024-2025 : 18 %
Up to Date : 100 %
Sanction on :
4 years 7 months ago
29 Nov 2019
Tentative Completion date:
2 years 6 months ago
31 Dec 2021
Actual Completion Date:
2 years 8 months ago
28 Oct 2021
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 09-Jan-2023
Physical Peramenters