Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 2.9 | 2.9 | 0 |
125W179 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2066/।।।(2)17-39(एम0एल0ए0)/2017 दि0 04.09.2017
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 17.68 Lacs
Resanction Cost : 17.68 Lacs
Exp. Upto Last Fy : 78.76 Lacs
For CFY 2024-2025
Remaining : -61.08 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 78.76 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
6 years 8 months ago
04 Sep 2017
Tentative Completion date:
1 month 1 week ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: CA Land
कार्यालय वनक्षेत्राधिकारी पैठाणी राजि0 के पत्रांक 598/12-1 दिनांक 12.02.2024 द्वारा क्षतिपूर्ति वृक्षारोपण हेतु ग्राम घण्डियाली पटटी काण्डरस्यू तहसील चैकीसैण के नाॅन जैड ए0 खतोनी की श्रेणी 10(4) अन्य कारणों से अकृषक भूमि खतोनी खाता संख्या 37 के खसरा सं0 367 मध्य 2.430 है0 भूमि सिविल भूमि को राजस्व विभाग व प्रस्तावक विभाग के साथ मौके पर जाकर संयुक्त निरीक्षण किया गया। उक्त चयनित भूमि वृक्षारोपण हेतु उपयुक्त पाई गई है जिसके क्रम मे इस कार्यालय के पत्रांक 272/2सी0 दिनांक 27.02.2024 द्वारा जिलािधकारी महोदय को उक्त भूमि को क्षतिपूरक वृक्षरोपण हेतु वन विभाग को आवंटित करने हेतु अनुरोध किया गया है। -- as on 01-May-2024
Physical Peramenters