Work Profile Report [125W349]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 903(1)/।।।(2)/21-39(एम0एल0ए0)201टी0सी0 दिनांक 30.03.2021
TS Amount (lakhs) : 62.26 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
62.26
Resanction Cost :
62.26
Tentative Cost :
62.26
Exp. Upto Last Fy :
57.85
For CFY 2024-2025
Remaining :
4.41
Demand :
0.45
Allotment :
4.41
Exp in CFY :
0.31
Total Up to Date Exp :
58.16
In Maintenance After Completion
Sanction on : 3 years 7 months ago
30 Mar 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 3 months ago
01 Aug 2022
Actual Completion Date : 2 years 4 months ago
07 Jul 2022
Physical Linear Components
Remark
कार्य पूर्ण। मार्ग अनुरक्षण अवधि में है। -- as on 08-Nov-2023
Assets :