Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 देहरादून के पत्रांक संख्या 895/07याता0-पी0एम0जी0एस0वाई0-नि0।।। दिनांक 16.05.2023
TS Amount (lakhs) : 125.11 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
125.11
Resanction Cost :
125.11
Tentative Cost :
125.11
Exp. Upto Last Fy :
74.73
For CFY 2024-2025
Remaining :
50.38
Demand :
50.38
Allotment :
1.21
Exp in CFY :
39.16
Total Up to Date Exp :
113.89
Work completed
Sanction on : 1 year 6 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 weeks ago
31 Mar 2024
Actual Completion Date : 9 months 2 weeks ago
05 Feb 2024
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व अवशेष। -- as on 26-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: