Work Profile Report [127W1]

श्री केदारनाथ धाम परिक्षेत्रान्तर्गत संगम घाट के पुनर्विकास का निर्माण कार्य (आई०ओ०सी०एल०)

    Fin Plan

    Remarks

    Tenders

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश संख्या - 1739/VI(1)/2020-03(10)/2020

TS Amount (lakhs) : 1547.8 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

1548.11

Resanction Cost :

1548.11

Tentative Cost :

1548.11

Exp. Upto Last Fy :

697.75

For CFY 2025-2026

Remaining :

850.36

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

697.75

Construction Started

Sanction on : 4 years 6 months ago

28 Sep 2020

Physical Progress:

At start of FY 2025-2026 :

60 %

Up to Date :

60 %

Tentative Completion date on : 2 years 8 months ago

31 Jul 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

Rating : 60

No Forest Case in The Work

No Hindrance / Bottleneck