Work Profile Report [127W10]
Fin Plan
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या - 1780/VI(1)/2020-03(20)/2020
TS Amount (lakhs) : 124.15 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
124.15
Resanction Cost :
124.15
Tentative Cost :
124.15
Exp. Upto Last Fy :
122.40
For CFY 2024-2025
Remaining :
1.75
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
122.40
Construction Started
Sanction on : 4 years 4 months ago
01 Oct 2020
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 2 years 7 months ago
23 Jun 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: Songanga bridge Garurchatti Bridge