Work Profile Report [127W3]

श्री केदारनाथ धाम परिक्षेत्रान्तर्गत प्राथमिक चिकित्सा पर्यटक सुविधा केंद्र निर्माण का कार्य (आई०ओ०सी०एल०)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks

    Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : शासनादेश संख्या - 2213/VI(1)/2020-03(10)/2020

TS Amount (lakhs) : 481.81 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

481.88

Resanction Cost :

481.88

Tentative Cost :

481.88

Exp. Upto Last Fy :

291.26

For CFY 2024-2025

Remaining :

190.62

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

291.26

Construction Started

Sanction on : 3 years 8 months ago

01 Dec 2020

Physical Progress:

At start of FY 2024-2025 :

90 %

Up to Date :

90 %

Tentative Completion date on : 1 year 7 months ago

22 Dec 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Buildings
1
1
1
-

Remark

view all

Rating : 90

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: Garurchatti Bridge