Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
128W110 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 3278/।।।(2)/17-04(एम0एल0ए0)/2015 दिं0 03.01.2017
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
48.35
Resanction Cost :
48.35
Tentative Cost :
48.35
Exp. Upto Last Fy : 2.33
For CFY 2024-2025
Remaining : 46.02
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.33
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 40 %
Sanction on :
7 years 6 months ago
03 Jan 2017
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
सरेखण प्रस्ताव स्वीकृत। वन भूमि पत्रावली दिनांक 23.12.2021 द्वारा आन-लाईन किया गया। डी0एफ0ओ0 के पत्र सं0 4396/12-1 गोपेश्वर दिनांक 24.02.2024 द्वारा वनभूमि हस्तान्तरण प्रस्ताव को परिवेश पोर्टल 2.0 में आनलाइन अपलोड करने हेतु निर्देशित किया गया। उक्त के क्रम में दिनांक 28.03.2024 को आनलाइन कर अ0अ0 के पत्र सं0 766/15सी0 दिनांक 28.03.2024 द्वारा डी0एफ0ओ0 को प्रेषित। वन भूमि प्रस्ताव नं0 एफ0पी0/यू0के0/रोड़/14464/2021 -- as on 02-Jul-2024
Physical Peramenters