Work Profile Report [128W24]

जनपद चमोली में गौचर-रानों-क्वींठी- सिमखोली मोटर मार्ग का विस्तार
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0ः-543 /।।।(2)/09-14 (प्रा0आ0)/08 दिनांक 11.02.2009

TS Amount (lakhs) : 153.72 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

330.75

Resanction Cost :

330.75

Tentative Cost :

165.00

Saving

165.75

Exp. Upto Last Fy :

127.06

For CFY 2024-2025

Remaining :

203.69

Demand :

10.84

Allotment :

10.84

Exp in CFY :

0.00

Total Up to Date Exp :

127.06

Work completed

Sanction on : 15 years 11 months ago

11 Feb 2009

Physical Progress:

At start of FY 2024-2025 :

80 %

Up to Date :

80 %

Tentative Completion date on : 2 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
9
3
3.000
0
0.000
0.000

Remark

view all

03 कि0मी0 हेतु वन भूमि की विधिवत स्वीकृति शा0 सं0 113/एक्स-4-18/ 1(169)/2016 दिं0 11.06.2018 द्वारा प्राप्त। कार्य पूर्ण। अवशेष 5.00 कि0मी0 लम्बाई में समरेखण प्रस्ताव अनुमोदित। अ0अ0 के पत्र सं0 484/15सी0 दिनांक 05.03.2024 द्वारा संयुक्त निरीक्षण की तिथि निर्धारित करने हेतु डी0एफ0ओ0 को पत्र प्रेषित। पुनः पत्रांक 982/15सी0 दिनांक 20.05.2024 द्वारा संयुक्त निरीक्षण की तिथि निर्धारित करने हेतु डी0एफ0ओ0 को पत्र प्रेषित। -- as on 04-Oct-2024

Rating : 82

Forest Case Pending At : 21: Final

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: