Work Profile Report [129W455]
Fin Plan
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 654/।।।(3)/2019-01 (सी0आर0एफ0)2019 दिनांक 30.05.2019
TS Amount (lakhs) : 903.86 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
903.86
Resanction Cost :
903.86
Tentative Cost :
903.86
Exp. Upto Last Fy :
903.48
For CFY 2025-2026
Remaining :
0.38
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
903.48
Work completed
Sanction on : 5 years 10 months ago
30 May 2019
Physical Progress:
At start of FY 2025-2026 :
51 %
Up to Date :
100 %
Tentative Completion date on : 2 years 10 months ago
01 Jun 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Jan-2023
Assets :