Work Profile Report [129W658]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-51297, लोक निर्माण अनुभाग-2 दिनांक 28.03.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
49.06
Resanction Cost :
49.06
Tentative Cost :
49.06
Exp. Upto Last Fy :
34.17
For CFY 2024-2025
Remaining :
14.89
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
34.17
Work completed
Sanction on : 1 year 10 months ago
28 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date : 1 year 3 months ago
18 Nov 2023
Physical Linear Components
Remark
कार्य पूर्ण। 11/2023 दायित्वों का भुगतान शेष। -- as on 27-Mar-2024
Assets :