Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
12W298 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1369/।।।(2)/16-69 (प्रा0आ0)/2015 दिनांक 21.03.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 39.40 Lacs
Resanction Cost : 39.40 Lacs
Exp. Upto Last Fy : 3.37 Lacs
For CFY 2024-2025
Remaining : 36.03 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 3.37 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 years 1 month ago
21 Mar 2016
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
दिनांक 08.02.2024 को उपजिलाधिकारी धारी द्वारा क्षतिपूरक वृक्षारोपण हेतु भूमि उपलब्ध करायी गई। जिसका वन विभाग के साथ दिनांक 20.02.2024 से 22.02.2024 के मध्य संयुक्त निरीक्षण किया जाना है। -- as on 19-Feb-2024
Physical Peramenters